Contractors Prepare to Set Gates to Close New Orleans Storm Surge Barrier

Text size: A A

Two, 550-ton sector gate leaves poised for installation next week in a $1.3-billion barrier being built to reduce risk of hurricane storm surge entering New Orleans’ vulnerable, eastern side, will plug a gaping hole in the city’s armor for the 2011 hurricane season.

Image courtesy USACE
Sector gates are part of a $1.3-billion barrier being built to reduce risk of hurricane storm surge entering New Orleans vulnerable, eastern side.
----- Advertising -----

On May 17, Massman Construction Co., Kansas City, Mo., is scheduled to begin installing the two 75-ft-wide, 42-ft-tall sector gate leaves that will form the armored door to a 150-ft-wide navigable passage through the northern end of the 1.8-mile-long barrier, which is know as the Inner Harbor Navigation Canal-Lake Borgne Storm Surge Barrier. It is part of a much larger defense system designed to reduce flood risk for the entire city.

When the gate is in place, the barrier will meet the U.S. Army Corps of Engineers design standards to reduce risk associated with a storm surge that has a one percent chance of occurring in any given year—often referred to as a 100-year storm.

“A lot of folks said it couldn’t be built,” says Col. (ret.) Vic Zillmer, Corps project manager on the IHNC. It is one of the largest features in the system, yet, by the end of April, the USACE and its contractors had completed roughly $980 million of the $1.1 billion construction cost of the +26 ft. elevation barrier.

Authorized by Congress in 2006, the IHNC barrier is designed to block smaller surges and reduce, or slow truly massive ones approaching from Lake Borgne and the Gulf of Mexico with heights greater than +26 feet, like the one that flooded portions of Orleans and St. Bernard parishes during Hurricane Katrina in 2005.

The IHNC surge barrier also includes a 150-ft-wide bypass barge gate, adjacent to the sector gate, and a 56-ft-wide vertical lift gate opening for recreational crafts where the barrier crosses Bayou Bienvenue. That gate is already set and is in the down and closed position. The barge gate—which is just that, a concrete-loaded barge designed to be intentionally submerged to block another opening in the event of a surge—will be on site by June 1 so it can be pulled into place if needed.

The sector gate is something of a marvel. “This sector gate has the highest storm design load of any structure in the world,” Zillmer says. “Our still water level is the same as the Dutch 10,000-year level. However, our wave load is much greater because we’ll have much bigger waves against the structure, and more of them.”

A joint venture of TetraTech INCA, Metairie, La. and Ben C. Gerwick, Oakland, Calif., designed the gate and supporting structure, which includes a 20-ft-wide ring wall curving from gate junctures to abutments to help the gate withstand tremendous storm surge loads.

The ring wall is 120 ft long and 42 ft high, from its sill under the channel to the roadway surface on top. It has a 3-ft-thick outer wall, a 2-ft-thick inner wall and 20-in.-thick connecting walls, Zillmer says.

“This type of wall was typical of fortified walls built in cities and castles for thousands of years, except the space between the inner and outer walls here is hollow due to weight considerations,” Zillmer says. But even hollow ring walls have precedent, he adds, such as one in a Biblical story about Jericho, which tells of a woman who lived inside the city wall and hid two spies there before lowering them out a window.

The gate leaves, which were fabricated at Shaw Global in Delcambre, La., are 42 ft tall and have an arc length of floodgate shield that is approximately 103 ft, says Larry Haser, vice president of operations management for Shaw Environmental & Infrastructure, Baton Rouge, the prime contractor.

The gate leaves arrived on site May 8 and are to be set in-the-wet, rather than inside a dry cofferdam. The contractor began pulling sheet piles to re-flood the cofferdam on May 10.

Installing the 550-ton gate leaves will be “very tricky,” Zillmer says, since each leaf must be attached at the pintle on the bottom, the thrust block in the middle and the hinge block near the top with a 1/8-in tolerance.

Massman will use a 600-ton crane and a 700-ton crane to move the gates from the transport barge to inside the flooded cofferdam. “The gates will be moved into final position using a system of push boats, winches and guides,” Haser says. “When accurately positioned, they will be sunk into final position in a controlled manner.”

 The gate structure foundation is supported by 478 steel pipe piles that are 154 ft long and driven to a tip depth of -178 ft. “When we built the barge gate next to it, using 2-ft-diameter square piles, we noticed a lot of movement,” Zillmer says. So instead of using the planned, 3-ft-dia. concrete square piles for the sector gate foundation, the contractor switched to 3-ft-dia. circular steel piles to reduce displacement.

Last July, Shaw’s subcontractor, TMW, a joint venture of Traylor Bros., Evansville, Ind., Massman and Weeks Marine, Cranford, NJ, drove the pilings during 6 p.m. to 6 a.m. navigation closures. “We only have four piles out of tolerance, and only by inches,” Zillmer says. “That’s quite an accomplishment for driving at night, underwater.”  

The cofferdam is larger than a football field: 163 ft by 383 ft, Zillmer says, and required a 10,251 cubic yard tremie slab. “It is one of the largest, continuous underwater concrete pours ever,” he says.

C.J. Mahan Construction Co., Grove City, Ohio, made the 58.5-hour continuous pour last October. “We had concrete truck operators from all over the country supplying the 160 CY per hour pour,” Zillmer says.

The 8-ft sill on top of the slab required 12 pours, each over 1,000 cu. yd.

At the end of April, the contractor was placing the last lifts on the thrust gates, ringwalls and abutments in preparation for the gate placement. “It will only take about four days to put the gates in, but we’ve planned 13 days in the schedule to accommodate wind and weather,” Zillmer says.

Shaw’s Haser says that remaining work on the IHNC surge barrier includes, but is not limited to: placement of scour protection at various locations; installation of mechanical, and electrical controls for the sector gates and barge gate; construction of approach walls; tower and bridge fabrication and erection at the Bayou Bienvenue gate; and mechanical, electrical and control systems at Bayou Bienvenue.

All three gates in the barrier are expected to be operational by this hurricane season, but will not be complete until 2012.

----- Advertising -----
Blogs: Texas & La. Staff
Our blog delivers the latest news, insights, and opinions about Texas & Louisiana construction.
Reader Photos
Photos from ENR Texas & Louisiana Photo Showcase
Dodge Lead Center
Search for local construction projects OR CALL 877-234-4246 and get a FREE Lead Now!
Search by Project Type & State





----- Advertising -----
 Reader Comments:

Sign in to Comment

To write a comment about this story, please sign in. If this is your first time commenting on this site, you will be required to fill out a brief registration form. Your public username will be the beginning of the email address that you enter into the form (everything before the @ symbol). Other than that, none of the information that you enter will be publically displayed.

We welcome comments from all points of view. Off-topic or abusive comments, however, will be removed at the editors’ discretion.