|
Finish Early If You Can
By Joseph P. Dirik, Esq.
The author recommends contractors
carefully consider whether or not to notify clients of a planned
early completion and when doing so, to submit a realistic
early completion schedule.
Joe Dirik is a graduate civil engineer and attorney. He is
a member of the construction law practice group at the Dallas
office of Jenkens & Gilchrist, PC.
It is often assumed that if a construction project is behind
schedule, the contractor must have problems with the project
and is likely losing money or, at least, not making as much
as intended. A project ahead of schedule, on the other hand,
is considered a sign of a successful job. So why not schedule
your project for early completion? I think this is a good
idea, particularly if the contract contains an early completion
bonus. But scheduling early completion may be problematic
if the owner interferes or otherwise delays the project.
If early completion is possible, there are many excellent
reasons why a contractor may choose this path. A shorter performance
time generally reduces indirect costs. Contractors may also
be able to avoid periods of inclement weather. Most important,
a contractor that focuses on early completion is probably
managing the project carefully.
The big problem facing an ambitious completion time involves
owner-caused delays or interference. What happens, for example,
if the contractor schedules completion three months early
and the owner causes three months delay? The answer depends
on the terms of the contract, the manner in which the contractor
schedules the project and ultimately how a Texas court or
arbitrator would chose to rule on the contractor's claim.
I haven't found a Texas case directly on point with this
issue, and other state case law is sparse. Federal courts
have addressed the issue in some detail and indicate that
while recovery is possible, it is difficult. The leading case
is Weaver Bailey Contractors Inc. v. United States. In this
case, the U.S. Army Corps of Engineers awarded a contract
for construction of breakwaters, requiring completion in February
of 1985. The contractor scheduled its work to complete ten
weeks early, in December of 1984, to avoid inclement weather.
As often happens, a defective design prevented the contractor
from meeting its early completion schedule. The government
refused to pay delay damages because the contractor had not
informed the government of the planned early completion. Interestingly,
the U.S. Claims Court, now the U.S. Court of Federal Claims,
ruled that notification was not required and awarded the contractor
more than $400,000 in delay damages. The court established
the following criteria under which a contractor may recover
for interference with scheduled early completion: the contractor
intended to complete the work prior to the contractual deadlines;
the contractor's intended schedule was reasonable; and the
contractor would have met its intended completion date but
for the delay or interference of the government.
The Weaver Bailey decision did not focus on whether the contractor
informed the government or that it intended to complete the
project before winter. Instead, the court focused on whether
the contractor would have completed the project early but
for the government's delay. Notwithstanding the court's position,
a Texas contractor should carefully consider whether or not
to notify its customer of a planned early completion. Consider
submitting a realistic early completion schedule to the owner.
By scheduling the project early, a contractor effectively
seeks to use project float. Many courts around the country
have concluded that float is owned by the project and is available
to the parties in the project as long as they act reasonably
and can demonstrate early good faith use of the float. Some
contracts contain float-sharing clauses that may control the
issue. A contractor's ability to effectively schedule early
completion may depend on how the contract treats float usage.
Although Texas courts have not dealt directly with this issue,
any contractor wishing to complete its project early must
have a plan to protect itself against owner-caused delays.
In addition, it is not enough for the customer to simply approve
an early completion schedule. The planned schedule must be
realistic. In order to prevail in a claim, the contractor
should be prepared to show that it would have been successful
in finishing early but for the customer's interference. Any
analysis should consider possible concurrent delay resulting
from the contractor's actions or inclement weather beyond
the customer's control. As in most schedule-related disputes,
the best claim is one that is based on a well-prepared and
well-managed schedule.
|