Opinions
 Blogs: Schwartz Stories
 Blogs: Other Voices
 Past Law/Courtroom
 Past Design
 Past Finance
 Past Better Business
 Past Sureties
 Past Guest Column





Law/Courtroom - November 2003

CONSTRUCTION LAW
"No-Damage-For-Delay" Clauses Are Here To Stay

By Joseph P. Dirik - Jenkens & Gilchrist

I was having lunch at the Barbecue Pit with Rodney, another lawyer from my firm when Bubba Wilson stopped by and asked if he could join us. "Of course" I said, "we were just talking about no damage-for-delay-clauses." "I'm glad I ran into you two" he said, "a contractor friend of mine just lost a big case because his contract included a no-damage-for-delay clause." "What do I need to know so that my company is prepared to deal with these clauses?" asked Bubba.

No-Damage-For-Delay Clauses

Rodney explained that Texas is among a number of states that rigidly enforce "no damage for delay" clauses because our courts generally believe in freedom of contract. Texas contracting parties are generally free therefore, to allocate the risk of construction delays between themselves.

The usual purpose of a no-damage-for-delay clause is to shift the risk for construction delays from the buyer of construction services to the seller of the services. These clauses are aimed at delays caused by the buyer or third parties. General contractors occupy both positions -- as a buyer (when contracting for subcontract services) and as a seller (when contracting with an owner). Your goals will necessarily be different in both situations. Buyers want broad coverage while sellers seek to limit the type of delay that falls within the no-damage-for-delay situation.

The no-damage limitation might not apply if the delays fall within one of several exceptions to the no-damage-for-delay clause. Two of the exceptions deserve special attention and might apply when the delay: (1) was not intended or contemplated by the parties to be within the scope of the clause; or (2) was the result of active interference by the buyer with the performance required by the seller under the contract.

Delay Not Within Contemplation of the Parties

It is difficult to successfully claim that the parties did not contemplate a particular delay if the contract contains a broad no-damage-for-delay clause. For example, Texas law suggests that unforeseeable delays be covered within a broad no-damage-for-delay clause.

In a leading Texas case on the subject, the court found that a broad no-damage-for-delay clause applied to both foreseeable and unforeseeable delays. The case involved a two-year contract to construct a passenger terminal at the Houston Intercontinental Airport turned into four years, due in part to several hundred change orders and over eight hundred requests for information. The contractor unsuccessfully argued that because it and the City did not foresee the great number of changes and requests, the no-damage-for-delay clause was unenforceable. The court rejected this argument and concluded that the purpose of a broad clause was to allocate the risk for unforeseeable delays and denied the contractor compensation for its delay damages.

Active Interference

Texas law also suggests that a general no-damage-for-delay clause cannot excuse the active interference of an owner that causes delays and resulting damages to the contractor. In a recent 1998 appellate case, the court refused to disturb a jury finding that the general contractor had actively interfered with its subcontractor's performance of the work. Examples of interference in the case included: (1) the general contractor's failure to coordinate and sequence the work of all the subs on the job; (2) improper surveying by the general contractor, and (3) the general contractor's failure to ensure that work completed by the subcontractor was not adversely affected by other subs on the job.

Enforcement of the No-Damage-For-Delay Clause

Most no-damage-for-delay clauses provide for a time extension as the sole remedy for the contractor in the event of construction delays caused by the owner. Some courts have found that an owner waives application of the no-damage-for-delay clause if it fails to grant such an extension for delays it has caused.

On the other hand, subcontractors and contractors may find they have forfeited their ability to challenge a no-damage-for-delay clause and recover for damages if they have failed to provide timely notice when required.

Contract Negotiation and Administration Tips

Rodney and I gave Bubba the following tips for contract negotiation and administration regarding no-damage-for-delay clauses.

When acting as the seller of construction services (general contractor or subcontractor):

Ask your lawyer to propose language that excludes unforeseeable delays from the scope of the no-damage-for-delay clause.

Always provide timely notice of delays, interference or hindrances caused by the buyer.

When appropriate, your notice of delay letter should characterize the event as one of the recognized no-damage-for-delay exceptions, rather than simply as a delay.

When acting as the buyer of construction services (owner or general contractor):

Ask your lawyer to propose a broad no-damage-for-delay clause that appropriately addresses intentionally caused buyer delays.

Your contract should include a notice provision for delays.

Always respond to a notice of delay and issue a time extension when appropriate if your no-damage-for-delay clause provides for this as the sole remedy.


 Click here for more Law/Courtroom News >>

advertisement

 


Sponsors

© 2012 The McGraw-Hill Companies, Inc.
All Rights Reserved