|
Cash-Flow Blueprints Too Often Overlooked
By Jim Jordan
 |
|
Jim Jordan is
director of construction services for Dallas/Fort Worth-based
Weaver and Tidwell LLP.
|
Contractors should protect their
financial health by carefully reviewing contract documents
and protecting cash flow.
For contractors, cash flow is what makes the world turn.
In an inordinately cash-intensive business, consistent cash
flow is mandatory if debt is to be kept in check and work
is to continue on schedule. More often than not, cash flow
measures a contractor's financial health better than even
net income.
Contractors typically bid jobs, win contracts and then sign
work documents spelling out how and when services will be
provided. The problem, however, is that many contractors do
not always understand provisions and terms in the documents.
It isn't uncommon for contractors to not read the contracts,
much less the general and supplemental conditions. That's
because many contractors perceive contracts to be nothing
more than standardized agreements that they have to accept
in order to get the job - a dangerous perception.
To protect cash flow, clauses dealing with payment are the
most important provisions. Such clauses explain when contractors
are going to bill and when the other party is going to pay.
They also specify the interest rate a contractor is to be
paid for late payments. To protect cash flow, the savvy contractor
will pay close attention to these clauses and not be timid
about requesting changes. For example, a contractor should
not hesitate to negotiate for payment in 30 days or less,
and should charge interest if the payment isn't made on time.
Often times a contractor does not want to upset the project
owner by pressing for timely payment or interest on late payments.
Contractors should not be afraid to negotiate for more favorable
retainage terms, such as a five percent retainage, if they
are providing a performance and payment bond. If the bond
is not being provided, a contractor still should negotiate
for a reduction in retainage once 50 percent of the work has
been completed. Also, contractors should get their retainage
as quickly as possible once the job is completed. The contractor
needs to ensure that terms do not allow excessive retention
for minor items. For example, a $1,000 punch-list item should
not hold up $10,000 or more in retainage. This happens all
too often.
In terms of back charges, contractors should require their
customers to notify them promptly of any proposed back charges.
Timely notification gives the contractor an opportunity to
correct the problem and avoid the back charge. Contractors
should never accept any back charge received months after
the fact. In particular, they should not accept it simply
to get their retainage.
Another issue that affects cash flow is stored materials.
Contractors often pay for materials and then store them at
the job site or a remote warehouse without being paid for
months. Instead they should negotiate payment terms for such
material by transferring title to the customer, having the
material tagged and physically safeguarded and insured. At
that point a contractor can be paid.
In addition to these issues, cash-flow-minded contractors
should pay special attention to other contract provisions
that carry significant ramifications for cash flow. Some of
these are:
Indemnity When a contractor
agrees to limited indemnity, he or she agrees not to hold
the owner responsible for damage caused by others. That's
reasonable. But by signing a provision for unlimited indemnity,
a contractor agrees to spare an owner from claims for virtually
all damages, injuries or loses - even those claims the owner
causes. Signing an unlimited indemnity is similar to blindly
giving away the bank: It means the contractor pays for everything.
Change Orders When extra
work is requested, contractors should bill for their work
as soon as it is completed and not accept change-order laziness
on the part of the project owner. The owner may not have the
money to pay for change orders once the project is completed.
A contractor should remember that he or she was a team player
in doing the work before the change order was written, so
the owner should also be a team player and pay in a timely
fashion even if the change order is delayed.
Warranties for Your Work
Any clauses related to warranties need to be closely inspected.
Here is a common scenario: An owner demands a multi-year warranty
from a general contractor on all aspects of a building, but
the general contractor's roofer only offers a one-year warranty.
The general contractor's risk begins in year two, meaning
he gets to pay for any problems with the roof. The easy solution
is to have the warranty terms be consistent.
|