|
Parking for Park Cities
For Dallas' New Baptist Church, the
Challenge Was All Underground
By Tonie Auer

An aerial view shows the limits
of the parking garage while under construction.
(Photo courtesy Austin Commercial
LP and John Bird Photography.) |
Building a three-story building atop a three-story underground
parking garage isn't easy.
Add to that, the project's proximately to a busy metropolitan
highway near a residential neighborhood and you've got more
than a few logistical hurdles.
For Park Cities Baptist Church in Dallas, growing pains led
church members and leaders to hire Austin Commercial LP of
Dallas to build a 315,000-sq.-ft. underground parking garage
and a 70,000-sq.-ft. building on a site that was formerly
the church's parking lot.
The $33 million project began in April 2004. The underground
parking garage was handed over in September and the church
building is scheduled for completion in the spring, said Monica
Schoenemann, senior project manager for Austin Commercial.
Schoenemann said the job was difficult because the site was
bordered by a residential neighborhood on one side and Northwest
Highway on the other. There also were access restrictions
and city mandates, she added.
"About 52,000 cars travel Northwest Highway every day
and that is our way in and out," Schoenemann said.
"The Texas Department of Transportation would never
allow us to shut down a lane of the highway, so we built a
little frontage road 15 ft. wide, and that was where all our
deliveries arrived. When a truck pulled up, we'd have to pull
material off quickly. We'd try to flag traffic and keep people
out of the lane next to us. But, just one lane over, cars
are going more than 55 mph."
Additionally, the city passed ordinances limiting work on
the project from 7 a.m to 6 p.m. and no Sundays. Also required
was an 8-ft. fence around the entire project to shield it
from the neighbors and no construction parking in the surrounding
neighborhood. Workers were bused in from east of Interstate-75,
Schoenemann said.
"I've done parking garages before, and some of them
have been huge," she said. "I've even done some
partially below grade, but this one is 35 ft. deep."
The garage was eventually built beneath the city roads, Shoenemann
said. Some roads were removed and replaced during the construction
project because the parking garage was taken out to the edges
of the property.
The completed garage can accommodate 750 cars compared to
the 174 parking spaces the church previously had, said Greg
Boyd, church member and project director/chairman of the construction
committee for the church.
The garage has an underground tunnel approximately 16 ft.
wide leading from the garage to the sanctuary, said Kip Jameson,
project architect for F&S Partners of Dallas.
"Because the church is located in a planned development
zone, the amount of land coverage they could have was limited,"
Jameson added. "We had to go through several calculations
with the city, and that is what led to the placement of the
parking garage underground. That way, we could maximize the
footprint and comply with the zoning."
Making the entire project fit on the site and allotting space
to accommodate as many cars in the garage as possible was
the first priority for the architects, Jameson said.
The architects had to design some deep and wide transfer
beams to carry the load of the building down through the garage
using post-tension transfer beams running the length of the
building, Jameson said.
"Because there was only a small amount of room to work
in, we had to accommodate a tremendous amount of staging,"
he added. "It was a monumental challenge sitting a building
on top of the parking garage. Structurally, it was an interesting
project. We were also limited on how tall we could build.
The city capped our height."
Boyd said the church was simply out of space in several critical
areas of its ministry and there also was a vast shortage of
parking.
The three-story building is adjacent to the existing campus
and will match its Georgian style of red brick with white
trim. It features 30,000 sq. ft. of space for preschool on
the first floor, approximately 26,000 sq. ft. in the form
of a grand hall on the second floor (with seating for 1,200)
and 14,600 sq. ft. for youth programs on the third floor.
As churchgoers come and go to and from the garage, elevators
will open primarily on level one into a 5,000-sq.-ft. commons
area, providing them with a foyer-style space for socializing.
Austin Commercial is also installing a new elevator in the
main sanctuary.
"That is unique, too, because the church was built in
the 1950s with all plaster construction," Schoenemann
said. "So any noise reverberated within the whole church.
"We're coordinating with the church on the sound. We've
had to saw out five slabs to put in a five-story elevator
in the existing church and chapel where events such as funerals
and weddings are taking place."
|
Key Players
|
| Owner:
|
Park Cities Baptist Church, University
Park |
| Architect:
|
F&S Partners Inc., Dallas |
| Structural
Engineer: |
Brockette/Davis/Drake Inc., Dallas |
| MEP
Engineer: |
Blum Consulting Engineers Inc., Dallas |
| Owners
Representative: |
Trammell Crow Co., Dallas |
| General Contractor: |
Austin Commercial LP, Dallas |
| Steel Contractor: |
North Texas Steel, Fort Worth |
| Concrete Contractor: |
Pecos Construction, Fort Worth |
| Retention System Contractor: |
Craig Olden Inc., Little Elm |
| Electrical Contractor: |
Walker Engineering Inc., Fort Worth |
| Plumbing Contractor: |
Don Burden & Associates Inc.,
Dallas |
| HVAC Contractor: |
Don Burden & Associates Inc.,
Dallas |
|