|
Holy Rosary's Revival
Historic Parish Gets New Life With Old
Stone
By Rob Patterson

An aerial view of Houstons
Holy Rosary Catholic Church, originally built in 1933
by Fretz Construction Co. The same contractor is giving
the church a $6.5 million makeover.
(Photo courtesy Fretz Construction.) |
Building a new 15,000-sq.-ft. parish hall and adding another
15,000 sq. ft. to the rectory of Houston's Holy Rosary Catholic
Church was a labor of love and devotion for Fretz Construction
Co. The church and the priory were originally built in 1933
by Fretz, whose current president, Bob Fretz Jr., is a member
of the parish.
The Houston-based firm overcame a series of major hurdles
to construct the $6.5 million project that began in July 2004.
The steel frame structures faced with complex limestone work
were designed by Marion Spears of MSA Architects Inc. of Houston,
also a parish member whose primary design work is in single-family
home design. Fretz took the basic plans and perfected them
beyond the normal scope of a general contractor's duties.
"The permitting process took nine months because the
documents weren't correct, so we actually had to step in and
get the drawings done ourselves because we knew what the city
wanted," said Terry Smith project manager for Fretz.
"We had our most experienced superintendent on the site,
and he picked up on a lot of structural things that simply
wouldn't work and had to be redesigned."
Fretz' role continued to expand. Early on in the job, architect
Spears left the business and closed his firm.
A nine-month permitting process meant meeting the original
scheduled completion date in July of this year wouldn't be
easy.
And, because of the urban church's location in Houston's
thriving Midtown neighborhood, the congregation was growing
and in dire need of more space to serve its members and the
community.
"When I came 10 years ago, our physical office space
was one room that was less than 200 sq. ft.," said Father
Joseph Kunkel, the parish priest. "We realized that as
the parish was reviving and more people were coming to the
area, we were operating under difficult circumstances."
A two-story, 1913-vintage parish hall was demolished to make
room for the new hall. "It actually had a 3-ft. below-grade
basement that served as a mechanical chase that no one was
aware of," Smith said. "And then underneath that
we found some 12 ft. piers that we had to dig out."
The new parish hall is three stories with offices and meeting
rooms on the ground level, a reception hall and kitchen on
the second floor and a third-story mechanical loft. The three-story
rectory addition added 10 new bedrooms and 11 bathrooms for
the parish priests and Dominican order brothers who work in
the community and reside in the church. The priory also boasts
a new chapel and public living room, dining room, kitchen,
community room and sunroom.
The new structures duplicated the original church and priory
design, including the use of Indiana limestone exterior and
Vermont slate roof. Masonry subcontractor Lucia Inc. of Houston
was able to obtain stone from Bybee Stone Co., the site of
the original quarry that provided the original 1933 materials.
The intricate ornamentation required expert work from the
stone subcontractor and suppliers.
"We made more than 50 plaster molds of the coping details
of the existing church building and sent them to Bybee Stone
in Indiana for duplicate details," Smith said.
Once work got under way, the project was six months behind
schedule. "Our superintendent, Ron Slavin, made up five
of those six months" through a combination of expert
scheduling and coordination of subcontractors, rapid steel
erection and working 10-hour days six days a week, Smith said.
"We base our reputation on meeting the schedule,"
Smith added. "Even though we were delayed, we still wanted
to see how close we could come to the original completion
date." The project came online in August, just one month
after the scheduled completion date.
The tight inner-city site posed further challenges. "Luckily,
we had a parking lot across the street that we were able to
occupy and put all of our staging on," Smith said.
Fretz also had to retrofit the existing HVAC and plumbing
and install a new chiller on the third floor of the rectory.
The company consolidated five gas meters and four water meters
into one for each utility.
Throughout the construction process, Fretz contended with
regulatory restrictions. "We had to come back in and
put in an eight-hour firewall in at one location," Smith
said. "So there were a lot of changes on the project
even after we got involved."
Fretz successfully worked around the daily parish activities.
"It was really not as obtrusive as you think it would
be," Kunkel said. "We weren't really disrupted."
Performing the job without an active project architect involved
gave Smith a new-found appreciation for designers. "We
always gripe at architects," he said. "But when
it comes time to get something changed, you go back to them.
"Here I was moving walls, coming back and drawing it
up by hand and sending it out to the subs. They were seeing
something they had probably never seen - a contractor doing
architectural work"
Prior to completion of the new structures, the exteriors
of the church and original rectory were cleaned. Smith said
the project replicates all the visuals of the 1933 building
including Gothic arches and ornamental embellishments such
as a fleurs-de-lis pattern.
"When you see the buildings, you would think they were
designed by the original architect." Kunkel said. "The
stonework is exquisite."
|
Key Players
|
| Owner:
|
The Archdiocese
of Galveston-Houston, Houston |
| General
Contractor: |
Fretz Construction
Co., Houston |
| Architect:
|
MSA Architects,
Houston |
| Structural
Engineer: |
Gaddy & Associates,
Houston |
| Masonry
Contractor: |
Lucia Inc., Houston |
|