|
Judges Awards-Industrial (Heavy)
and Design
Judges Award-Industrial (Heavy)
Deer Park Energy Center
Submitted by:
Zachry Construction Corp., San Antonio
Location: Deer Park
Key Players:
Owner: Calpine Corp., Folsom,
Calif.
General Contractor: Zachry
Construction Corp., San Antonio
Architect/Engineer: Burns
& Roe Enterprises Inc., Oradell, N.J.
Zachry Construction Corp. of San Antonio served as general
contractor/manager for the the $193.3 million three-phase
Deer Park Energy Center. The project called for the construction
of a four-on-one cogeneration facility to provide up to 2.5
million lbs. per hour of steam to plant host Shell Complex
and electricity to the Electric Reliability Council of Texas
utility grid.
The project began on Sept. 24, 2001, and was completed in
May.
Phase one included the installation of the initial heat-recovery
steam generator/combustion-turbine generator and supporting
infrastructure, including a water- treatment unit, underground
services in the 12-acre power block, a main pipe rack and
an auxiliary cooling tower.
Phase two included installation of a second heat-recovery
steam generator/combustion-turbine generator. The first and
second phases operate out of the same powerhouse, using an
auxiliary three-cell modular cooling tower.
In Phase three, Zachry installed the third and fourth heat-recovery
steam generator/combustion-turbine generators, a steam-turbine
generator and the main cooling tower. All phases were completed
ahead of schedule and with an excellent safety record.
During the project, 2.3 million labor work hours were expended.
At completion, the center is made up of four Siemens-Westinghouse
501F combustion-turbine generators, four Nooter-Eriksen heat-recovery
steam generators and a 275 megawatt Toshiba steam-turbine
generator.
The team used bolted tanks for the project as opposed to
conventional welded tanks, which eliminated the need for coating
and meant a lower total installed cost to the project. The
quicker assembly time also allowed other craftworkers to begin
work ahead of schedule.
Shorter pilings saved time and money. After a series of piling
tests, Zachry recommended that the 1,800-plus pilings be shortened
from 65 ft. to 48 ft., making the pile driving easier and
quicker.
Zachry employed flowable-concrete fill at the project site,
allowing for placement with minimal effort and saving schedule
time and labor versus placing and compacting soil or granular
material.
Among the creative solutions employed to operate efficiently
within the tight work area was the integration of a smaller-than-normal,
fully enclosed SF6 insulated switchgear electrical interconnect
unit. The 345,000-volt unit allowed for placement in a relatively
small two-acre site, which subsequently allowed for a smaller
switchyard.
A shortage of sufficient laydown area became apparent during
planning. Because the project trailers and installed equipment
occupied the 12-acre work area, a 300-ft. apron on the north
side of the powerblock was provided as additional laydown
area. This was accomplished through a temporary construction
easement. Zachry constructed offsite material laydown and
employee parking on the easement.
Judges Award--Design
SkyLink Automated People Mover
Submitted by: Kellogg
Brown & Root (KBR) Inc., Dallas
Location: Dallas/Fort Worth
International Airport
Key Players:
Owner: Dallas/Fort Worth
International Airport Board
Design, Design Management, Construction
Administration and Quality Assurance: Kellogg Brown
& Root (KBR) Inc., Dallas
Design Team: KBR Inc, Dallas;
CAGE Inc., Dallas; Chiang, Patel & Yerby Inc., Dallas;
Evan Evans Associates Inc., Dallas; Freese & Nichols Inc.,
Fort Worth; Johnson-McKibben Architects Inc., Dallas; LOPEZGARCIA
GROUP, Fort Worth; PSA Constructors Inc., Orlando; Teng &
Associates Inc., Chicago; URS Consultants Inc., Dallas; Williams-Russell
& Johnson Inc., Atlanta
General Contractor/Construction
Manager: Hensel Phelps Construction Co., Greeley, Colo.
Architect of Record: Corgan
& Associates Inc., Dallas
Structural Engineer of Record (stations):
Fresse & Nichols Inc., Fort Worth
Structural Engineers of Record
(guideway): KBR Inc., Dallas; URS Consultants Inc.,
Dallas; Teng & Associates Inc., Chicago; Freese &
Nichols Inc., Fort Worth
Dallas/Fort Worth International Airport's new 5-mi.-long,
dual-track, bidirectional Automated People Mover system has
an initial performance capacity of 5,000 passengers per hour
per direction.
The system will have a two-minute headway between trains
and will carry passengers to the farthest interconnection
point on the airport in only nine minutes at speeds of up
to 37 mph. The APM system traverses the secure side of the
airport, allowing passengers to interconnect without passing
through security checkpoints.
The 25,400-lin.-ft. guideway structure has two independent
bidirectional lanes. The guideway is a continuous loop that
extends along the airside face of four existing terminals
and through the interior space of the new Terminal D.
Construction of the guideway is equivalent to building a
5-mi. elevated bridge structure while having aircraft operate
and function underneath. The guideway alignment between terminals
follows the airport's existing public service roadway system,
adding to the construction challenges.
The north and south ends of the guideway alignment also span
across existing public/service roadways, which had to remain
operational.
The guideway superstructure consists of either concrete
U-beams or steel trapezoidal-box beams topped with an 8-in.-thick
concrete deck supported by post-tensioned concrete columns.
The columns, which range in height from 50 ft. to 70 ft.,
have an elliptical shape with strong vertical/horizontal reveals
and a dimension of 5 ft. by 7 ft.
The APM program schedule was the driving constraint of the
project. From the start of design, the $45 million program
required that initial service to the public be provided in
60 months. The general contractor had to complete the last
section of the guideway and the propulsion power substations
within 33 months.
The consolidated design/construction schedule was coordinated
to meet this contractual obligation and required aggressive
design and construction sequences. Construction began in 2000
and was completed by the end of 2004.
The design team, led by Kellogg Brown & Root, was made
up of engineers, architects and designers from 15 subconsultant
firms, with 66 percent being minority/women-owned business
enterprises.
Pricing packages were developed for early procurement of
long-lead and bulk items that would be used throughout the
airport by multiple subcontractors. Bid packages were developed
for units of work that paralleled the contractor's subcontracting
plan and installation critical path.
|