|
Canvassing With Concrete
Ribbons of Concrete Roads Wind Through Central
Texas
By Rob Patterson
|

At more than 100 ft., placing cranes and man lifts on
SH 45 at its interchange with U.S. 183 was no simple
task for contractor Austin Bridge & Road. (Photo
courtesy Austin Bridge & Road.)
|
Texas is leading the nation in highway construction, and
one of the epicenters of work is Central Texas, where a number
of current projects involve high complexity and innovative
approaches to working with concrete. Some of those methods
may become more common based on their successful use on these
jobs.
Austin Bridge & Road, an operating company of Dallas-based
Austin Industries, is more than 85 percent complete on Section
8 of the new SH 45 toll road in north Austin, a job that includes
a five-level interchange with U.S. 183 and a toll plaza stretching
across 22 lanes, as well as extensive utility relocation along
the 2.5-mi. stretch. Construction started in December 2003
on the $105 million project. It will be completed by the end
of next month.
The first phase of the project involved relocating electric,
gas, water and telecommunications utilities along the SH 620
corridor that SH 45 is replacing. Austin Bridge & Road
installed 14,000 ft. of new water and waste conduits, 40,000
ft. of storm sewer and relocated aerial electric and cable
lines into an underground duct bank. Four lanes of asphalt
access road were then built to carry SH 620 traffic before
work could begin on the new roadway.
"We had a lot of contractors, subcontractors and outside
utility companies working simultaneously," said Mike
Brown, project manager for Austin Bridge & Road. "The
coordination was more involved than normally required."
The most complex aspect of the project was the interchange.
Austin Bridge and Road built four of its levels while Austin-based
J.D. Abrams, the contractor on the intersecting section of
the U.S. 183 project, built another level. "It is more
than 100-ft. tall," said Robert Vallejo, general superintendent
for Austin Bridge & Road. "We had to lift massive
concrete and steel girders around obstacles and existing roads."
The interchange required 14 man lifts and 12 cranes to perform
the work. "Because of the existing traffic, it was difficult
to stage all of the equipment," Brown said.
Liquid nitrogen was used to cool the concrete for all the
mass pours on the footings and pilings (see "Beating
the Heat," page 67). The contractor installed 1.2 million
ft. of bridge deck on the structure.
Austin Bridge & Road also constructed an operations building
and a 400 ft. long 10 ft. by 10 ft. box culvert underneath
the barrier plaza for its communications and control systems
and to give staff access to stations.
A 190-ft. section of fiberglass-reinforced jointed concrete
paving from 11- to 17-in. thick was installed around the toll
plaza. The remainder of the SH 45 roadway is 11-in.-thick
steel-reinforced concrete.
The contractor poured 125,000 cu. yds. of concrete overall
on the project.
|

To facilitate TxDOT's aim for more aesthetically pleasing
retention walls, Speed Fab-Crete of Fort Worth precast
Ashlar stone panels for the Zachry/Gilbert job on Loop
One in Austin.
|
Brown said the sheer volume of the job and its schedule were
the project's major challenges. "TxDOT has a goal of
early completion," he said. "The efforts of our
people reflect that sense of accountability to meet and exceed
these expectations."
On a nearby stretch of road, a joint venture of San Antonio-based
Zachry Construction Co. and Gilbert Texas Construction of
Austin has been performing similar work on a 3.5-mi. toll-road
extension of Loop One. Construction began in August 2003,
and the $108 million project is scheduled to complete by the
end of next month.
The job includes three bridges, six ramps, a main toll plaza
and three ramp plazas. A section of FM 1325 and associated
utilities had to be relocated as part of the project.
Zachry/Gilbert poured 107,000 cu. yds. of steel-reinforced
concrete and more than 3,600 cu. yds. of fiberglass-reinforced
concrete at the plazas. The job included 1.1 million cu. yds.
of excavation, 2 million cu. yds. of embankment and 500,000
cu. yds. of precast concrete walls.
The volume of work was a challenge for Zachry/Gilbert. Recovery
work following the 2005 hurricanes impacted the availability
of utility crews. "We had to stretch our equipment, manpower
and materials," said Jean Abiassi, director of operations
for Zachry's highway/heavy group.
TxDOT hired PBS&J of Miami to act as a management and
inspection consultant on both jobs due to the amount of highway
work being performed in the Austin area. "That added
a new dimension to doing work with TxDOT," Brown said.
For TxDOT, the coordination of multiple contractors working
simultaneously on adjacent and nearby projects wasn't easy.
Minimizing the effects of work on businesses and residents
and keeping traffic flow going were concerns for the agency.
"The projects will result in a big improvement in traffic
flow in the area," said Jeff Tolson, TxDOT project supervisor.
He added that the projects are ahead of schedule and under
budget.
|

The bridge decks for the IH-35/Loop 340 interchange
in Waco were prepared in a precast yard near the job
site. Archer Western Contracting of Arlington served
as the projects general contractor.
|
About 100 mi. north of Austin in Waco, the $44 million IH-35/Loop
340 (SH 6) interchange reconstruction project was a test program
of an alternative approach to creating and erecting a precast-concrete
bridge on four of the five bridges. Archer Western Contractors
of Arlington set up a precasting yard about a mile from the
job where column liners were cast and deck and rails were
placed on tub girders that were assembled into the bridge
deck.
To achieve the decorative design on the columns, they were
poured into upside-down forms with one layer of rebar using
533 cu. yds. of concrete. After being set on the site, the
interiors were poured in place.
The bridge spans were laid out in the yard, using 104 separate
tub girders. The decks were poured and, on the outside girders,
rails attached. Then the modular pieces - each 115 ft. long
and 8 ft. wide and weighing about 185,000 lbs. - were separated
and transported to the site.
Some creativity was needed to haul and maneuver the large
pieces. "We used steerable dollies and John Deere
tractors," said Bill Heathcott, senior project manager
for Archer Western.
It took just two night shifts to lift all pieces into place
using two cranes. All that was required next was a closure
pour to a 12-in. gap between the beams.
"In a typical operation you'd then have to set overhangs
and decking after placing the beams, and both operations would
impact the traffic," Heathcott said. "You'd have
to follow with a deck pour and setting the rails. The only
time traffic was impacted was the beam set. The closure pours
were made without traffic closure and the rail and deck was
cast prior to erection in the precast yard."
Two older bridges were demolished, and one new bridge connecting
eastbound Loop 340 with northbound IH-35 was built using conventional
methods. Archer Western also rerouted utilities and performed
extensive site work on the project, performing 260,000 yds.
of excavation, building 230,000 yds. of embankment and pouring
138,000 sq. yds. of concrete paving for the on-grade ramps.
"I think the setting of the beams and the deck was a
success," Heathcott said. "We bid a job in Bell
County recently that had a similar deck orientation."
But precasting columns didn't save time, he added.
"We feel that the test was a success, and were pleased
that we were able to limit the closures and detours,"
said John Jasek, Waco area engineer for TxDOT.
About 50 mi. southeast, on a $26 million job on SH36 in Cameron,
James Construction of Baton Rouge, La., performed a variety
of tasks including the demolition of a 4,200-ft., vintage
1940s bridge across Little River and constructing two new
bridges. The firm built four mi. of divided concrete roadway
and constructed a new railway bridge over the road.
The three-phase project started in August 2004 and is more
than 50 percent complete with a July 2007 finish date.
The first phase included the construction of the first new
3,000-ft., two-lane bridge to carry SH36 traffic and allow
demolition of the old bridge. The contractor was concerned
about safety during the demolition of the old steel girder
bridge while it still perched precariously above the river.
Engineered Explosive Services of San Antonio solved the problem
by blasting the pilings of the bridge after the center span
over the river was removed. Most of the structure was dropped
to the dry riverbed where it could be safely demolished.
During phase two, the second two-lane bridge was built. The
two bridges were constructed on concrete pilings with precast
concrete and steel beams and 244,000 sq. ft. of concrete bridge
deck.
A 150-ft. reinforced concrete railroad bridge was built over
the SH 36 roadway. At 17-ft. high, it has three ft. more clearance
than the old railroad bridge, which was demolished after tracks
were rerouted.
The final phase was construction of the four mi. of expanded
four-lane on SH 36. More than 50,000 cu. yds. of concrete
was poured atop a base of flex mix and asphalt.
"The variety of work and trades made it an interesting
project to work on" said Ken Janke, Texas division manager
for James Construction.
"Once the project is completed, it will significantly
improve access on SH 36 to the Cameron area," said Bob
Cochran, TxDOT area engineer for the Milan District.
|