|
Concrete Forms and Secures
North Texas Plant Takes Water Treatment
Indoors
By Rob Patterson
|

The buildings at the Tom Harpool Regional Water Plant
in Aubrey were constructed behind a berm to obscure
them from an adjacent housing development. (Photo courtesy
of Oscar Renda Contracting.)
|
At first glance, the form of the $33 million Tom Harpool
Regional Water Treatment Plant in Aubrey doesn't match its
function. With the processes and controls enclosed in two
steel-frame and roof structures faced with spilt-face CMU,
it could easily be mistaken for an attractive warehouse facility.
That was the goal of the Upper Trinity Regional Water District.
Roanoake-based Oscar Renda Contracting began construction
in December 2004 on the project, which is aiming for a September
completion.
Since a housing development is adjacent to the 86-acre site
- formerly a horse ranch - minimizing the plant's visual and
operational impact on its neighbors was a major element in
its design. "Upper Trinity builds nice facilities, and
they were especially concerned with that because it is so
close to residents," said Jim Gallovich, project manager
for Carollo Engineers PC of Dallas, designers of the plant
and the developers of the water district's master plan.
"What is unique about this plant is that with most conventional
water treatment plants, the processes are outdoors in concrete
basins," said Paul Mendoza, project manager for Oscar
Renda. The Harpool plant encloses its innovative membrane-filtration
process inside a 25,000-sq.-ft. building. Another two-story,
8,000-sq.-ft. structure houses administrative functions and
the chemical feed and control equipment.
"There was 600,000 cu. yds. of excavation and dirt moving
to get the site to the proper contours that had to be done
before we started construction," Mendoza said. The excavated
material was used on site to create a berm to hide the plant
from nearby homes. A pre-existing sand pit on site reduced
the excavation needed to create two clay-lined ponds about
an acre each in size to hold the backwash from the plant.
Excavation for the concrete filtration basins went 12 ft.
below grade, and a four-million gallon pre-stressed concrete
well required a 24-ft. dig. "The bottom of the excavation
was about five ft. below the groundwater table," Mendoza
said. "So we built our own small de-watering system around
it while we were building it up.
"To prepare the concrete tank site, we had to put in
eight ins. of flex base below the tank that had to be shaped
to within .25 in., all by hand," Mendoza said. "We
had a dozen guys with shovels and a grade checker doing the
work."
The four-million gallon tank, which is 195 gallons in diameter,
used 5,000 cu. yds. of concrete. The 72-in. inlet and outlet
ports on the tank also had to be surrounded by 100 cu. yds.
of concrete to ensure they were not affected by movement or
foundation problems.
|

Workers smooth a concrete surface on the control building
of the water plant. (Photo courtesy of Oscar Renda Contracting.)
|
Another 7,000 cu. yds. was poured for the 13 intricately
formed filtration basins that are in the basement of the membrane
building. With the addition of the control building, pump
stations and junction structures, a total of 17,000 cu. yds.
of concrete was poured on the job.
The majority of the concrete work being at or below grade
was a boon for the project. "We poured about 90 percent
of the concrete with a crane and bucket," Mendoza said.
"We didn't have to use pump trucks, and that saved us
money."
Although the well and basins required 880 tons of rebar,
the contractor was not affected by recent steel shortage or
price hikes. "We had our steel locked in price-wise,
and hopefully our supplier didn't get hurt," Mendoza
said. "The concrete shortage hasn't really impacted us
either, though we did have to schedule deliveries a week in
advance."
A design change from the usual scheme for membrane filtration
systems did present a challenge. "Typically the pipes
come up on top of the tanks," Gallovich said. "We're
running them through the sides and created these pipe galleries.
This is one of the first facilities that Xenon, the membrane
manufacturer, had performed this on, so we couldn't cut and
paste things."
|

The design of the buildings enclosing the water treatment
process disguise its functions. (Photo courtesy of Oscar
Renda Contracting.)
|
The plant was also on a fast track to provide 20 million
gallons a day to meet the needs of the water district's member
municipalities and water supply corporations in the booming
region north of Dallas. "We had such a short period of
time to get it online because of the drought situation,"
said Randy Sliger, project manager for the Upper Trinity Regional
Water District.
The schedule and the site required extra coordination. "We
had multiple concrete crews working simultaneously, sometimes
half a mile away," Menoza said.
Among the reasons that the water district chose the membrane
process was for its expandability. The master plan calls for
the plant to eventually treat 260 million gallons a day.
|
Key Players
General Contractor:
Oscar Renda Contracting Inc., Roanoke
Owner: Upper
Trinity Regional Water District, Lewisville
Architect/Structural
Engineer: Carollo Engineers PC, Dallas
Concrete supplier:
Southern Star Concrete Inc., Irving
|
"All the piping has provisions for future connections,"
Mendoza said. "The district spent quite a bit of extra
money on oversized piping , additional inlets and outlets
and Y fittings so that when expansion does occur, it will
minimizes the shut-down time and reduce the amount of modifications
needed."
Enclosing the treatment process inside a building makes the
plant more secure than outdoor facilities. "It is going
to be one of the first ultra-filtration membrane plants with
Xenon filters in this area," Sliger said. "It takes
a smaller footprint for this type of plant than a conventional
plant, and that is going to be the trend of the future."
|