|
Refined Design at Clear Lake
Hospital Adds Two Floors After Fourth Level
Complete
By Lesley Hensell
|

In addition to a new heart hospital, DPR Construction
built a 400-ft. pedestrian bridge over a busy county
road. It connects the new structure to the existing,
35-year-old facility. (Photo courtesy DPR Construction.)
|
When it seemed there was no good way to make room for new
patients, Clear Lake Regional Medical Center charted a roundabout
path for growth.
The Houston-area hospital struggled to find an effective
method for expanding its round-shaped, 35-year-old facility.
Tying in the existing building's circular shape would make
new construction difficult, so the hospital instead launched
plans to centralize cardiac care in a new heart hospital.
Construction began in July 2005 on the $90 million heart
hospital, which will be connected to the medical center by
a pedestrian bridge. With approximately 84 beds, the heart
hospital will increase the campus' capacity to 454 beds and
will house operating rooms, intensive care beds, a coronary
care unit, catheterization laboratories and private inpatient
beds. To help the new heart hospital tie visually with the
existing round hospital, the rectangular building features
a rounded glass curtain wall in the front, said Mark Roan,
an associate at the Dallas office of architecture firm Perkins
+ Will.
The two buildings are connected by a 400-ft. pedestrian bridge
over a busy county road. With roughly 100 tons of steel, the
bridge was assembled primarily on the ground in modular sections.
Once those sections were ready, the street was closed down
so that they could be lifted into place.
"Probably one of the more challenging parts of the project
was the connector bridge itself, with all of the restrictions
and entities we had to coordinate through," Roan said.
"We also were tying into an existing building with set
floor-to-floor heights." The air-conditioned bridge has
been finished off with metal panels and glass, while the heart
hospital's skin includes a combination of glass, masonry,
stucco and metal panels, said Troy Ireland, project manager
for Austin-based DPR Construction, the general contractor.
Extra care had to be taken at the project's outset due to
the sandy, unstable soil on the seven-acre site.
"We did some massive excavation to get the footings
done about 8 to 11 ft. below grade," Ireland said.
When ground first broke, the hospital intended to construct
a facility of 160,000 sq. ft. over four stories. But months
into the construction process, the hospital exercised its
option to add another two floors to the project, bringing
the total square footage to 210,000, Ireland said.
"Our original goal was to finish the concrete structure
on March 15 of '06," Ireland said. "The hospital
had always intended on future vertical expansion, but around
December, we got the word that they were ready to go ahead
and pull the trigger while we were here. We incorporated the
added work and completed the structure for all six floors
just two weeks after our original deadline."
|

Pouring the 6,000 yds of concrete for the new structure
required about 70 workers be onsite. The team used a
Peri Formwork System for pours of about 15,000 sq. ft.
each. (Photo courtesy DPR Construction.)
|
The additional floors also required slightly different specifications,
which created an even greater time crunch, Ireland said. The
project is slated for completion in March 2007, although the
top two floors will not be finished out until a later date.
"We are close to the bay, where there are a lot of sandy
soils," Ireland said. "Based on the site's soil-bearing
capacity, when the two floors were added, we could only do
so much in concrete, with the rest in steel. Concrete goes
quicker than steel does."
The architect chose cast-in-place concrete for the building's
structure for several reasons, Roan said.
"The symmetrical shape of the building and the uniformity
of the column bay distances allowed for a lot of repetitive
form use, which led us toward concrete" Roan said. "We
could have built it out of steel, but the lead times were
simply too long. Concrete and the labor needed to get it in
place were more readily available."
To ensure that the cast-in-place structure's 6,000 yds. of
concrete were quickly poured, subcontractors had about 70
workers onsite up to six days a week, Ireland said.
"We were fairly fortunate that while we were working
on most of the structure, we didn't get a ton of rain,"
he added. "We lost about two weeks during Hurricane Rita
last year. We have not seen problems with material shortages."
Key
Players
Owner: Hospital
Corp. of America, Nashville
General Contractor:
DPR Construction, Inc., Austin
Architect: Perkins+Will,
Dallas
Structural Engineers:
Design Electric, Houston
Concrete and Sitework:
Keystone Concrete Placement, Houston
Steel: Myrex
Industries, Houston
Mechanical and Plumbing:
Polk Mechanical Co., Houston |
During the cast-in-place concrete portion of the project,
a four-story tower crane was installed on the site.
"When we were told that the additional two stories would
be going up, we spent a weekend lifting the crane 30 ft. to
accommodate them," Ireland said. "There was a scramble
to get the equipment in place quickly, so we could stay on
track."
For the cast-in-place work, the team used a Peri Formwork
System for pours of about 15,000 sq. ft. each.
"We tried to do about a pour a week," Ireland said.
"With that fast pace, we had a lot of questions that
had to be resolved with the structural engineer on the fly."
The addition of two floors also meant that the building would
be considered a high-rise and under different building codes.
"The added floors put us into a higher wind-load bracket,
since we are close to the coast and have to allow for hurricane-force
winds," Ireland said. "This has affected the design
of exterior framing systems, as well as the glazing system.
There are now an entirely new set of safety rules in place."
|