|
Garage Mahal
University of Houston
Ramps Up With New Parking Facility
By Lesley Hensell
|

The northwest corner elevation at night.
|
Not all parking garages are created equal. Especially at
the University of Houston, where a new mixed-use parking structure,
with its complex construction scheme, will offer plenty of
parking space as well as finished-out areas dedicated to retail
and academics when it reaches final completion this month.
Built on an existing surface parking lot at Calhoun Road
and University Drive, the $25.8 million garage encompasses
519,000 sq. ft. over five levels. It provides 1,500 parking
spaces, as well as a 25,000-sq.-ft. academic and welcome center
and 10,000 sq. ft. for retail use on the building's first
floor.
The garage is a "mixed-use structure that will help
to enhance campus life," said Dave Irvin, associate vice
chancellor and associate vice president for facilities and
plan operations at the University of Houston. "There
will be great synergy with all parts of the building - retail,
the visitors' center and the academic center. Visitors will
be able to buy tickets for different events on campus, while
prospective students and parents will be able to learn more
about admissions and financial aid."
The garage relies on express ramps, which raised the degree
of difficulty for its design and construction.
"With this design, there are flat decks with an express
ramp at one end," said Matt Elliott, project manager
for SpawGlass of Houston, the general contractor. "This
creates a more efficient flow of traffic and a larger area
of flat deck. The flat deck is attractive from a constructability
standpoint, but the express ramp is pretty complicated."
Unlike regular ramps in garage designs, express ramps are
intersected by deck columns at different heights on different
levels of the structure. As a result, it was more difficult
to design, form, reinforce and place the columns, Elliott
said.
"The express ramp design has several advantages,"
Irvin said. "First, it allows a clear view of every floor
of the garage, which is key to enhancing security. Also, our
master plan is to expand the garage in the future. With this
design, we can simply add more flat parking space on the other
side of the ramp using a single ramp to quickly load the entire
garage."
|

Coordination and scheduling in the heart of a large,
active university area meant pours were scheduled beginning
at 1:00 a.m.
|
Work on the fast-track project launched in January 2005,
and the parking portion of the facility opened just 12 months
later - ahead of schedule and just in time for the spring
semester. To accomplish this, the SpawGlass team set up an
aggressive pour schedule for the garage's cast-in-place concrete
structure. Each of the garage's 109,000-sq.-ft. decks was
split into five sections of approximately 25,000 sq. ft. each.
"To cycle the formwork properly and meet the schedule,
we created a 25-week pour schedule," Elliott said. "In
most cases, we worked after-hours for the formwork and reinforcing
placement. All concrete placements were started at 1 a.m.
on a Friday morning."
This late-night schedule helped the team work effectively
in a congested university environment by allowing concrete
staging, off-loading and clean-out at less-active times.
"By Monday morning at 7 a.m., the cylinders were broken
at the testing lab," Elliot added. "That gave us
the rest of the week to wreck the formwork and move on to
the next two areas to get ready for the next Friday-morning
pour."
To ensure that there was enough time to move on to the next
area, the team invested in a premium 4,000 psi mix that guaranteed
a 3,000 psi break within three days. That way, the team could
start stressing post-tensioned cable within three days.
"A couple of times, to speed things up, the lab broke
cylinders on Sunday mornings," Elliott said. "We
did end up working quite a few weekends."
As the team worked through concrete pours, project managers
took extra care to document the locations of post-tensioned
cables, which became particularly important as work began
on the finish-out of the first-level indoor spaces, Elliott
said.
Key
Players
Owner: The University
of Houston System, Houston
Construction Manager
at Risk/General Contractor: SpawGlass, Houston
Architect:
STOA/Goleman/Bolullo Architects,
Houston
Structural
Engineers:
CBM Engineers Inc., Houston
MEP
Engineers:
Infrastructure Associates Inc., HoustonCivil
Engineers:
Jaymark Engineering Corp., Houston
Reinforcing: Texas
Cold Finished Steel Inc., Houston; Suncoast Post-Tension,
Houston;
Reinforcing
Placement:
Doran Steel Inc., Houston
Concrete
Materials: Transit
Mix Concrete & Materials Co.,Beaumont
Concrete
Placement:Alpha Delta Concrete, Houston
Masonry: Camarata
Masonry Systems,Houston
Curtain
Wall: Floyd's Glass Co., Houston |
"Since the finished spaces are on the first level, we
knew there would be a lot of equipment and materials hanging
from the deck above," he said. "Since it is full
of post-tension cables, there was a big concern that one of
these cables could be ruptured when subcontractors went to
anchor a piece of equipment in the deck above.
"We went to great lengths to identify cables so that,
when we started building out below, it would be easy to know
exactly what was going on."
For the columns on the project, SpawGlass chose white Portland
cement for its lighter color. But the quick-setting nature
of the cement required tweaks to forming and placement techniques.
"That mix in and of itself is kind of volatile, so we
had to play with it to keep it workable long enough to pour
the columns and make them look good," Elliott said.
In addition to more convenience, the parking garage will
offer additional security to students and staff. Administrators
have installed video cameras and blue-light security phones
throughout the garage, and a University of Houston police
officer is stationed at the building. The lighting is nearly
twice that in an average garage.
Nestled among oak trees, the garage was designed to aesthetically
match other campus buildings. It features a skin of face brick,
glazed tile and cast stone.
"Inside and out, the garage was built to be much more
than simply a place to park," Elliott said. "It
truly enhances the campus around it."
|