|
International Terminal D
Submitted by: DFW Airport
Location: DFW Airport
Key Players:
Owner: Dallas/Fort Worth International Airport
Construction Manager at Risk: Austin Commercial Inc., Dallas
Design Architect: HKS Inc., Dallas
Architect of Record: Corgan Associates Inc., Dallas
Lead Design Architect: HNTB Cos., Kansas City, Mo.
Parking Garage Architect of Record: Gresham Smith and Partners,
Dallas
Structural Engineer: L.A. Fuess Partners Inc., Dallas
Civil Engineers: Carter & Burgess Inc., Fort Worth, and
LOPEZGARCIA GROUP, Dallas
MEP Engineers: Friberg Associates Inc., Fort Worth, and Blum
Consulting Engineers Inc., Dallas.
A design-build project, M.D. Anderson Cancer Center Ambulatory
Clinical Building, totaling 781,700 gross sq. ft., was designed
as the "signature" building on M.D. Anderson's site,
housing cutting-edge technologies within an environment of
spacious lounges and rooftop gardens utilizing natural lighting..
The building's lower five floors are built from 130,000 cu.
yds. of cast-in-place concrete, while the upper seven floors
are structural steel. The team decided to transition between
the two materials after examining ways to optimize the grid
for a parking garage and a first-class health-care building.
.
To meet M.D. Anderson's aggressive schedule, the team elected
to transfer the load from concrete to steel on level two,
as the building would be speedier to erect using structural
steel. Level two now features large concrete transfer girders
to accommodate the larger column spacing in the underground
parking garage.
Health Care
Baylor Medical Center at Irving Medical Office Building and
Educational Conference Center
Submitted by: MEDCO Construction, Dallas
Location: Irving
Key Players:
Owner: Healthcare Realty Trust, Nashville, and Baylor Health
Care System, Irving
General Contractor: MEDCO Construction
Architect: PageSoutherlandPage, Dallas.
.
Baylor Medical Office Building II is a 127,000-sq.-ft. office
building intended to house medical practices of varying sizes
and create an atmosphere where education is a driving force.
.
The new five-story facility features a wireless network, wiring
to support the latest technology, a conference center with
seating for up to 300 people, self-contained kitchen, sky
bridge, after-hours card key access system and space for a
variety of medical practice. .
One highlight of the facility is the education center, a large
conference room that can be converted into two, three or four
smaller rooms. The closets, on two sides of this room, contain
walls that slide on rails to convert the area into smaller
rooms..
Sensors located along each rail electronically notify the
lighting system as to whether the room has been divided and
allow each individual room to control its lighting. .
The conference center contains a wireless network that allows
computers and projectors to function without cables. It features
a self-contained kitchen area so Baylor employees don't have
to prepare food offsite.
Health Care
Baylor Radiosurgery Center, Gamma Knife and CyberKnife
Submitted by: MEDCO Construction, Dallas
Location: Dallas
Key Players:
Owner: Baylor Health Care System
General Contractor: MEDCO Construction
Architect: Henningson, Durham, and Richardson, Dallas.
The 2,500-sq.-ft. Gamma Knife/CyberKnife project includes
patient rooms, teaching room, waiting areas, a staff conference
room and two large vault-type rooms for the Gamma Knife and
CyberKnife.
The type of technology involved with the Gamma Knife and CyberKnife
is revolutionary. The Gamma Knife consists of a hollow helmet-shaped
half-sphere of metal, perforated by 201 holes that all point
to the center of the sphere. .
By positioning the patient's head so the tumor lies in the
sphere's center, a large dose of radiation can be given to
the tumor while sparing the surrounding tissue. Because the
patient's head must be placed precisely within the sphere
a metal frame is mounted to the skull. .
CyberKnife is slightly different from the Gamma Knife; no
head frame is required. Instead a robotic device guides a
linear accelerator around the patient, stopping periodically
to deliver one beam at a time. The CyberKnife's advantage
is its potential for treatment of tumors throughout the body.
Physicians are investigating the use of this treatment for
tumors located in the lungs, liver, kidney, pancreas, prostate
and breast.
Health Care
Hybrid Operating Room Suites
Submitted by: Linbeck Group LLP, Houston
Location: Houston
Key Players:
Owner: St. Luke's Episcopal Hospital
General Contractor: Linbeck Group LLP
Architect: RTKL Associates, Dallas
MEP Engineer: SSR Engineers, Houston.
The Texas Heart Institute at St. Luke's Episcopal Hospital
in Houston is the third health-care facility in the United
States to construct hybrid operating suites. These rooms are
extremely complex in both function and appearance. .
The hybrid procedure is an innovative approach to treating
coronary artery disease. It allows minimally invasive heart-bypass
surgery and angioplasty in the same operation. Although these
two procedures are not new, combining them into one surgical
procedure is. .
A hybrid operating procedure requires the participation of
12 to14 health-care professionals. To maximize space and to
enhance staff safety while performing their jobs, the only
item that connects to the floor is the base of the surgical
table. All other equipment is suspended from the ceiling.
The exception is a three-part robot, used for telesurgery,
in which a surgeon manipulates the robot to perform surgery
from a remote location..
Once the parameters for the suites were set, the team began
the process of reconfiguring the space. Since the suites are
located in the hospital's heart institute, extreme care was
essential to safeguard the sterility of the environment.
Health Care
University of Texas Southwestern, Medical Center Phase IV
Submitted by: Austin Commercial LP, Dallas
Location: Dallas
Key Players:
Owner: University of Texas System, Austin
Contraction Manager at Risk: Austin Commercial LP
Architect: Omniplan Inc., Dallas.
The University of Texas Southwestern Medical Center is a
recognized leader in studying and developing treatments for
diseases such as multiple sclerosis, cancer, Alzheimer's,
Parkinson's and problematic cholesterol..
With the completion of the phase four campus expansion, UT
Southwestern added approximately 1 million sq. ft. to its
current biomedical research facilities, allowing the incorporation
of fields such as neurology, pharmacology, biochemistry, histology,
DNA sequencing and developmental biology into its research
curriculum. .
UT Southwestern is also a teaching facility for approximately
3,500 medical, graduate and allied health students, residents
and postdoctoral fellows each year. .
The new phase four biomedical facility encompasses a total
of 760,000 sq. ft. of new facilities, including a 16-story,
558,000-sq.-ft. research tower with underground parking; 372,000-sq.-ft.
interstitial research support building parking structure with
a landscaped plaza; expansion of the existing thermal energy
plant; and site and utility infrastructure..
The faculty dining area contains a full kitchen and dining
area with the capacity to serve 208 people. There also is
an elegant, 154-seat executive dining area. .
The conference center features a 60-person conference room
as well as three, 20-person conference rooms.
Higher Education/Research
Harte Research Institute, TAMU
Submitted by: Zachry Construction Corp., San Antonio
Location: Corpus Christi
Key Players:
Owner: Texas A&M University
General Contractor: Zachry Construction Corp. and Centex Construction,
Dallas
Architect: Richter Architects, Corpus Christi, in association
with Watkins Hamilton Ross Architects, Houston
Civil Engineer: MEI Govind Inc., Corpus Christi
Structural Engineer: Walter P. Moore Engineers + Consultants,
Houston.
The Harte Research Institute Building is a $13.36 million,
three-story scientific research and teaching facility. Scientists
from Cuba, Mexico and the United States will use the facility
as a place to study the Gulf of Mexico, part of a collaborative
effort to ensure its long-term use and conservation.
Zachry/ Centex's work on the HRI included construction of
research and teaching laboratories for marine biochemistry,
environmental geochemistry and fisheries and aquaculture specialties.
Facilities include a seawater lab, wet and dry research labs,
shell space for future labs, a GIS computing lab and shared
laboratory support areas. The building houses administrative
offices and a conference center.
Curtain walls offer a view of the Corpus Christi Bay. The
building was designed with windows that face north and south,
which helps deflect heat from the sun. Masonry walls make
up the uniquely curved walls of the staircase and conference
center.
Each of the seven warped walls was constructed using reinforcing
steel and fully grouted cells in 12-in. block, concrete masonry
units. This served as a backup to the corbelled brick veneer.
Industrial
Beaumont Cogeneration Project
Submitted by: Zachry Construction Corp., San Antonio
Location: Beaumont
Key Players:
Owner: ExxonMobil Corp., Beaumont
General Contractor: Zachry Construction Corp. as part of Jefferson
County Power Partners, San Antonio
Civil and Structural Engineer: Black and Veatch, Overland
Park, Kan.
.
ExxonMobil Oil Corp. selected Jefferson County Power Partners,
a joint venture between Black & Veatch and Zachry Construction
Corp., to provide complete engineering, procuring and constructing
services for the Beaumont Cogeneration Facility.
The Beaumont Cogeneration Power Project was constructed over
a two-year period on a piece of property located less than
500 ft. from neighborhood homes and families.
ExxonMobil acquired the land from the city and had it de-annexed.
Jefferson County Power Partners and ExxonMobil worked together
to balance the construction aspects of this project with the
local community's concerns. By hosting regular information-sharing
meetings with the neighborhood, ExxonMobil and JCPP were able
to mitigate the project's impact on residents' daily lives.
The facility is a multiple-unit combustion turbine and heat
recovery steam generator facility that provides 480 MW of
electricity and 1,500 psig steam production. The plant uses
a 3X3X0 configuration that incorporates three General Electric
7FA combustion turbines and three Nooter/Eriksen HRSGs.
The units are single-fuel, natural-gas-fired and the HRSGs
include selective catalytic reduction for emissions control.
Commercial operation is planned for mid-2006.
K-12
Rutledge Elementary
Submitted by: American Constructors LP, Austin
Location: Leander
Key Players:
Owner: Leander Independent School District
Construction Manager: American Constructors LP, Austin
Architect: Tew Associates, Austin
Civil Engineer: PBS&J, Austin
Structural Engineer: L.M. Swayze Engineers, Austin
MEP Engineer: MEP Engineering Inc., Austin.
Leander ISD wanted to provide a new elementary school for
the fast-growing Austin suburb that would be energy efficient,
highly resistant to mold, have a minimum 50-year durability
and express the style and stature of the existing structures
in the district.
American Constructors and architect Tew Associates traveled
to Florida, North Carolina and Ontario, Canada, to find the
right solution: site-precast tiltup wall panels with integral-composite
insulation and thin brick veneer.
The handsome building resembles masonry construction but is
made of thin brick cast directly into the tiltup wall panels
utilizing the Versa Liner system provided by Innovative Brick
of Louisville, Colo.
The school evokes the images desired by the school district:
strength and durability with a modern look that connects to
the values of the past.
The exterior tiltup wall panels also feature 2-in.-thick
expanded polystyrene insulation integrally cast into the panels
using the Thermomass System by Composite Technologies of Boone,
Iowa. A key benefit of the system is the elimination of cavity
wall construction that can contribute to the growth of mold
in buildings.
Private Building
Federal Reserve Bank
Submitted by: Linbeck Group LLP, Houston
Location: Houston
Key Players:
Owner: Federal Reserve Bank of Dallas, Houston Branch
Construction Manager/Builder: Linbeck Construction Group LLC
Architect: Michael Graves & Associates
Structural Engineer: Walter P. Moore Engineers + Consultants,
Houston.
.
The Houston Branch Building Project is a 297,000-sq.-ft.
facility with a total of seven separate building structures
intended to be a 50-year-plus facility.
The Houston Branch Building Project is the first Federal Reserve
Bank facility constructed under the new Federal Reserve System
Facility & Security Guidelines issued after Sept. 11.
The project served as the first installation of many new,
upgraded design and construction features to thwart the threat
of terrorism. The nature of the bank's operations obviously
requires a sophisticated building and site security system,
utilizing the latest technology in all components and individual
systems.
One of the core functions of the Federal Reserve Bank is the
processing and storage of currency and coin for local banks.
The Houston Branch Building Project included construction
of the second-largest currency vault in the Federal Reserve
Bank system, with inside clear dimensions of 58 ft. wide,
166 ft. long and 67 ft. high.
The vault floor/foundation consists of a 36-in.-thick concrete
mat, and the vault walls and roof are thick heavily reinforced
cast-in-place concrete.
All concrete building structures on the campus were built
entirely with crews from Linbeck, including concrete formwork,
reinforcing steel placement and concrete placement and finishing.
Public Building
METRO Downtown Transit, Center and Admin Building, Houston
Submitted by: Manhattan Construction Co., Houston
Location: Houston
Key Players:
Owner: Houston Metropolitan Transit Authority
General Contractor: Manhattan Construction Co.
Architect: PGAL Architects, Houston
Engineering Consultants: Walter P. Moore Engineers + Consultants,
Houston
MEP Engineer: I.A. Naman + Associates Inc. Consulting Engineers,
Houston.
The new Metropolitan Transit Authority Administration Building
is a 14-story office building that houses METRO administrative
offices and also provides an important transit center function
for METRO customers who are transitioning between bus and
light rail service.
The new METRO building anchors the development of a full city
block in the heart of downtown Houston.
Construction includes a poured-in-place pan slab concrete
structure with post-tension girders, architectural precast
with punched windows on two sides and glass curtain-wall cladding
on two sides.
The new home for METRO also includes a nine-bay covered bus
transit center with a vaulted, standing-seam metal roof and
curved glass skylights. Overall, the administration building
project size totals 395,000 gross sq. ft., and the transit
center represents 25,000 sq. ft.
Interior finishes include a ground-floor lobby area that
is open to the second floor, with finishes that include Gascogne
Blue limestone walls and terrazzo flooring. The second floor
lobby provides access to the 3,500-sq.-ft. boardroom that
comfortably seats 150.
Renovation/Restoration
Cathedral Guadalupe Tower and Steeple
Submitted by: Andres Construction Services, Dallas
Location: Dallas
Key Players:
Owner: Roman Catholic Diocese of Dallas
General Contractor: Andres Construction Services
Architect: ArchiTexas, Dallas
Engineer: Jaster-Quintanilla, Dallas.
Designed by renowned Texas architect Nicholas Clayton, the
cathedral was dedicated on October 26, 1902, as the Sacred
Heart Cathedral. It is one of the last remaining examples
in Dallas of the High Victorian Gothic style.
In 1975 the cathedral combined its congregation with that
of the former Guadalupe church of Dallas, and in 1977 it became
the Cathedral Shine of Our Lady of Guadalupe.
The bell tower/ steeple construction renovation is part of
a master plan to restore and renovate the cathedral for its
role in modern-day Dallas while respecting the structure's
history and architecture.
The 225-ft. bell tower was part of Clayton's original design,
but because of lack of financial resources at the turn of
the century the Cathedral choose to build an 85-ft. tower
with a temporary roof with the hopes of completing the construction
in the future.
More than a century later Andres Construction Services had
the opportunity to complete the architect's vision.
The outside perimeter of the tower is 20 ft. by 20 ft.; the
tower construction is all load-bearing masonry, including
8-ft.-deep by 7-ft.-wide masonry-grade beams. The new mat
foundation is 35 ft. by 35 ft. by 8 ft. deep, with two sides
of the foundation excavation on the interior side of the church.
Holes were saw cut through the existing masonry beams and
foundation rebar was threaded through them to combine the
old and new foundation into one.
Renovation/Restoration
Sunset High School, Addition and Renovation
Submitted by: McCarthy Building Cos. Inc., Addison
Location: Dallas
Key Players:
Owner: Dallas Independent School District
Program Manager: Jacobs/Pegasus, Dallas
General Contractor: McCarthy Building Cos. Inc.
Architect: BCI Architects, Dallas
Mechanical Contractor: Federal Mechanical Systems, Carrollton
Electrical Contractor: Design Electric, Dallas.
The project involved completing a $9 million, lump-sum bid,
HVAC upgrade and interior renovation to Sunset High School,
a 155,000-sq.-ft. building, which was originally built in
1925, and constructing a new 50,000-sq.-ft. classroom addition
in 10 months, one week and one day.
That might not sound all that tough, but throw in a host of
other schedule constraints and combine those with the fact
that school started on Aug. 15 and the city awarded the certificate
of occupancy on Aug. 12.
McCarthy attributed its success to its onsite project-management-based
approach and to having an excellent electrical subcontractor
that performed well beyond expectations.
Design Electric started the project based only on a trusting
relationship with McCarthy developed on two other projects.
They started on a promise of: "When we finish the value-engineering
process and receive the contract from DISD, we will send you
one."
This trusting relationship allowed the procurement of the
main electrical gear necessary for the power conversion to
take place before "contract agreements" were officially
in place.
Renovation/Restoration
The Tower
Submitted by: Turner Construction Co., Dallas
Location: Fort Worth
Key Players:
Owner: TLC Development, Fort Worth, and Greenfield Partners
Inc., Chicago
Construction Manager: Turner Construction Co.
Design Team: Corgan Associates Inc., Dallas, and GideonToal,
Fort Worth.
Originally built in 1974, the Tower, one of Fort Worth's
first skyscrapers, was scheduled for demolition after a tornado
struck and severely damaged the building in 2000.
When the owner decided to implode the building in 2002, it
was discovered to be too dangerous to public health because
of the potential for asbestos entering the air.
TLC Realty Advisors recognized the high-rise residential potential
of the damaged property and worked with the owner and the
city of Fort Worth to finance the project, forming a partnership
with Greenfield Partners in 2003.
Turner Construction Co. was brought in early to provide preconstruction
and construction management services for the renovation and
conservation of the 37-story building.
The final renovation consists of 511,000 sq. ft. of residential
space, 290 condominiums and four penthouses as well as 135,000
sq. ft. of retail and commercial office space.
Renovation/Restoration
Warwick Terrace
Submitted by: SpawGlass Construction Corp., Houston
Location: Houston
Key Players:
Owner: Warwick Towers
General Contractor: SpawGlass Construction Corp.
Landscape Architect: Kudela & Weinheimer, Houston
Structural Engineer: French Engineering, Houston.
The Warwick Towers, located in the heart of Houston's Museum
District, had a vision for the creation of a rooftop terrace
for residents.
SpawGlass self-performed $300,000 in concrete work. The project
consisted of the demolition of the existing landscaping and
waterproofing, as well as selected structural concrete demolition
of the planter beds, existing water feature, building expansion
joints, overlay slabs and ramps.
All of the work was done on the fifth floor of the parking
garage while the entire high-rise condominium remained occupied
and operational.
The project had to be built using a narrow 50-ft. access area
on the north side of the building. Every piece of material
that was installed throughout the project had to be lifted
to the site by a crane or other hoisting mechanism at a single
location. The entire block had to be shut down in order to
accommodate the 175-ton crane needed to reach the roof.
The rooftop oasis is now a resort-like space with several
decorative concrete patterns, shrubs and trees, three-tiered
fountain, putting green, copper-roofed gazebos, tennis court,
jogging trail and areas for barbecuing.
Transportation
Access Control Points Project
Submitted by: M.W. Builders of Texas Inc., Temple
Location: Killeen
Key Players:
Owner: U.S. Army Corps of Engineers
General Contractor: M.W. Builders of Texas Inc. .
The Access Control Points Project began as an $18,577,000
project to upgrade all the major entry gates into the Fort
Hood military installation.
The project required the construction of 21 entry-gate facilities,
two truck inspection facilities and one visitor control center
building.
Each entry facility, or ACP, included a gatehouse for guard
operations and a canopy covering all lanes of inbound traffic
for identification and verification of vehicle traffic. There
also were extensive site upgrades such as widening of existing
inbound and outbound lanes, concrete medians, concrete-lined
ditches, new electrical site and roadway lighting, new chain-link
fencing and metal-beam guard rail, new pavement marking and
traffic signage, and new utility and infrastructure upgrades.
There were three types of ACPs constructed on the project,
depending upon their use, location and extent of traffic flow.
Five primary ACPs, 10 secondary ACPs and six housing/limited-use
ACPs were built to meet a wide variety of access control needs.
The project included the construction of two truck inspection
facilities to be utilized by security forces to inspect, X-ray
and verify all truck traffic entering Fort Hood.
The project also included the construction of a new 2,800-sq.-ft.
visitor control center building to serve as the main hub for
all new visitors to the installation.
The ACP project grew to a current contract amount of more
than $28 million through numerous owner-requested changes
to include additional security measures.
Transportation
State Highway 45
Submitted by: Zachry Construction Corp., San Antonio
Location: Austin
Key Players:
Owner: Texas Department of Transportation, Texas Transportation
Authority, Pflugerville
General Contractor/Manager: Zachry Construction Corp. and
Gilbert Construction LP, Fort Worth
Civil and Structural Engineer: PBS&J, Pflugerville.
The project, along with the Loop 1 extension, SH-130 and
U.S. Highway 183 A will eventually be the four connected toll
elements comprising the 122-mi. Central Texas Turnpike Project.
The CTTP is the biggest and most expensive toll-road work
ever undertaken in Texas.
The CTTP aims to increase mobility and improve travel safety
in Central Texas, but other benefits such as economic development
are expected as well.
The project is a joint venture, known as ZGC, between Zachry
and Gilbert Texas Construction LP, with Zachry assuming the
lead. The project is located approximately 1 mi. west of Interstate
35 at FM 1325, north of Austin in Round Rock.
The project encompasses the construction of an interchange
facility connecting new SH-45N with Loop 1. It includes pavement,
base, grading, drainage and illumination.
ZGC self-performed most of the work on the project, including
earthwork, lime stabilization, roadway grading, concrete paving
and box culvert, drainage and bridge construction.
|