|
Best of 2004-Hospitality
Gaylord Texan Resort & Convention
Center
Submitted by: Centex Construction
Co., Dallas
Location: Grapevine
Key Players:
Owner: Gaylord Entertainment,
Nashville
General Construction: Centex
Construction Co., Dallas
Architect: Hnedak Bobo Group
Inc., Memphis
Civil Engineer: Carter &
Burgess, Dallas
Structural Engineer: Uzun
& Case, Atlanta
MEP Engineer: J&A Mechanical
Inc., Grapevine
The Gaylord Texan Resort and Convention Center located on
Lake Grapevine is just minutes from Dallas/Fort Worth International
Airport. The project, which broke ground in March 2001 and
debuted in April, includes a 1.3 million-sq.-ft. hotel with
1,511 rooms, a 786,000-sq.-ft. convention center, numerous
restaurants and retail space.
The $515 million complex was designed with extensive stonework,
themed landscaping and replicas of the Alamo and the San Antonio
Riverwalk to illustrate the Lone Star state in every detail.
The project features three atriums totaling 4.5 acres of
intricate glass-and-steel structures that represent the Riverwalk,
the Hill Country and Palo Duro Canyon.
The Centex team had 26 months to transform 57 acres of former
North Texas farm country into more than 2 million sq. ft.
of resort space that included simulated rivers running through
the air-conditioned, themed-atrium spaces.
Centex's immediate solution was to assemble a large team
of preconstruction and operations experts to guide the life
of the project. Early involvement during preconstruction proved
invaluable.
The columns supporting the ballroom level are 33 ft. tall
and include a large amount of reinforcing steel. Rather than
placing concrete from the top of the form, the team placed
the concrete from the bottom by attaching a pump-hose coupling
directly to the bottom of the column form. A column-hung forming
system was then utilized to place the ballroom concrete floor.
The ballroom level boasts 24-ft.-tall ceilings adorned with
chandeliers and crown molding.
Best of 2004-Renovation/Restoration
University of Texas Frank C. Erwin
Jr. Special Events Center
Key Players:
Submitted by: Hensel
Phelps Construction Co., Austin
Owner: The
University of Texas System, Austin
General Contractor: Hensel
Phelps Construction Co., Austin
Architect/Engineer:
Heery International Inc., Atlanta
Hensel Phelps was the general contractor for about $38 million
worth of improvements and renovations to the 17,725-seat Frank
C. Erwin Jr. Special Events Center, originally built in 1977
to house basketball games for the University of Texas at Austin.
Upgrades included meeting current fire and life-safety requirements.
The project was broken into two phases and was completed
in March.
During stage one, new arena seating arrangements were provided
to create a more exciting basketball environment by moving
fans closer to the court. The courtside seating brings fans
7 ft. from the court as compared to the original 20 ft.
Concession stands, new restroom facilities and 28 luxury
suites were constructed during stage two. The new skyboxes
provide suite holders access to private wet bars, catering,
an in-suite television, private restrooms and special parking
accommodations.
Hensel Phelps had to demolish and relocate existing concourse
concession stands and restroom facilities to make way for
the 28 luxury skyboxes. The project featured several unusual
design and construction techniques from the lavish, customized
finishes in the suites to the various food service venues.
The project doubled the concession stand capacity and tripled
restroom facilities. Hensel Phelps implemented a rigorous,
job-specific quality control plan that included control of
onsite construction, detailed mock-ups, offsite inspections,
shop drawings and submittal reviews.
ADA and life-safety improvements included the addition of
a new code-compliant fire alarm and sprinkler system. All
exterior doors were replaced and the curtain wall removed
and relocated outward to enlarge the main concourse. Additional
exits were added from the arena floor including the east stair
exit, which required a tunneling operation to occur inside
the building.
Best of 2004-Public Building
Austin City Hall and Public Plaza
Submitted by: Hensel Phelps
Construction Co., Austin
Location: Austin
Key Players:
Owner: City of Austin
General Contractor: Hensel
Phelps Construction Co., Austin
Architect: Antoine Predock,
Albuquerque
Associate Architect: Cotera
+ Reed, Austin
Structural Engineer: Datum
Engineering Inc., Austin
MEP Engineer: ACR Engineering
Inc., Austin
The city of Austin selected Hensel Phelps to build the new
$33.3 million City Hall and Public Plaza overlooking Town
Lake. The team of the fast-track project, which broke ground
in January 2003, worked toward a Silver LEED certification.
Completion was set for November.
The tight site in the heart of downtown Austin required strict
material controls and traffic planning.
Dominated by landscaping, the green building incorporates
limestone, copper, glass, water and shaded areas. The terraces
and limestone balances resemble the natural features of the
Texas Hill Country and are prime locations for viewing the
activities of the Public Plaza below.
The completed project will feature water that flows from
the front steps of the building to splash over limestone rocks
in the exterior plaza. There a limestone amphitheater and
stage will host special events and cultural performances.
Trellises of photovoltaic and copper mesh panels will shade
spectators.
The team devised two exceptional construction innovations
to save money without sacrificing quality or aesthetics.
The first was a copper roof system originally designed by
Bill Zaner, who has patented a beautifully paneled roof with
a built-in system to enable water to be captured and flow
to the ground. Hensel Phelps worked with the supplier and
subcontractor to devise a panel system that still retained
the copper appearance but without the complex draining system,
saving more than $1.5 million.
The second was the exterior skin. The original design called
for a tiered system of limestone, beginning with 12-in.-thick
blocks of limestone and stepping up by increments of four.
The resulting weight of the limestone, large pieces and difficulty
of cutting made the skin expensive.
Hensel Phelps devised a plan to cut the limestone into 4-in.-thick
blocks and tiered concreted masonry units with the limestone
blocks, retaining the same appearance of the original design
but at a far less cost.
Best of 2004-Health Care
Round Rock Medical Center Cardiac
Catheterization Lab/C-Section Suite
Submitted by: DPR Construction
Inc., Austin
Location: Round Rock
Key Players:
Owner: St. David's HealthCare
Partnership, a partnership between HCA, Nashville, and St.
David's HealthCare System, Austin
General Contractor: DPR
Construction Inc., Austin
Architect: Perkins &
Will, Dallas
Civil Engineer: Baker-Aicklen
& Associates Inc., Round Rock
Structural Engineer: L.A.
Fuess Partners Inc., Dallas
MEP Engineer: Smith Seckman
Reid Inc., Nashville
The $3.45 million project at the Round Rock Medical Center
included the addition of a 5,000-sq.-ft. cardiac catheterization
addition, 450-sq.-ft. caesarean section room expansion and
the build-out of 29 medical/surgical patient rooms totaling
9,600 sq. ft. The project began in February 2003 and was completed
the following February.
Construction took place alongside, above and within occupied
hospital areas. Preserving a sterile environment through proper
infection control procedures was of foremost importance.
DPR's infections disease control program, which incorporates
traditional occupied hospital building procedures enhanced
with practices developed in semiconductor cleanrooms, includes
step-by-step processes for creating pretask plans, performing
the work and documenting steps taken.
To ensure areas adjacent to construction remained clear
of dust or debris, DPR utilized negative air machines to create
a vacuum in the rooms under construction, ventilated contaminated
air out of the building and used gauges to constantly monitor
the rooms' air pressure. The project manager developed a custom
alarm system that rang whenever there was a change in pressurization,
allowing the team to make adjustments before there was any
possibility of contaminated air entering occupied areas.
The new Cardiac Catheterization Lab portion of the project
was built to replace a temporary unit on the hospital campus.
The project manager had to pinpoint the exact day of turnover
two months in advance so the hospital could arrange for no
downtime.
DPR used three-week rolling schedules, updated daily, to
carefully track field activities, ensuring work was complete
and ready to pass inspection. The project was turned over
to the hospital several days prior to the mobile unit being
taken offsite.
Best of 2004-Sports/Entertainment
Texas A&M Bright Football Complex
Submitted by: SpawGlass,
Houston
Location: College Station
Key Players:
Owner: Texas A&M University
System, College Station
General Contractor: SpawGlass,
Houston
Architect: O'Connell Robertson
& Associates Inc., Austin
Structural/Civil Engineer: Jaster-Quintanilla
LLP, Austin
MEP Engineer: O'Connell
Robertson & Associates Inc., Austin
The 125,000-sq.-ft. Bright Football Complex at Texas A&M
University was built next to Kyle Field, the largest stadium
in the Big 12 Conference.
The largest facility of its kind in the nation, the $27
million Bright Complex houses a locker room, athletic training
room, rehabilitation complex, meeting rooms, coaches' offices,
players' lounge and academic area.
With 15,000 sq. ft. of space, the new athletic training
room is more than four times larger than the previous facility.
The Hagner Auditorium seats more than 250 teammates, coaches
and staff.
On the second level, an entire 28,000-sq.-ft. area provides
academic services such as computer facilities, quiet study
areas and counseling sites. SpawGlass constructed a 50-station
computer lab, study lounges and eight classrooms in the academic
center.
A center core three-story concrete shaft wall is the focal
point of the complex. The glass-like "Spatula Stui"
finish applied to the concrete wall has the appearance of
maroon and white marble. The main wall and stainless steel
grand stairway were all constructed on the same radius to
create a unified look. The main wall entrance has .75-in.
solid wood paneling with a finish consistent throughout the
facility.
Among the challenging aspects of the project were the arched
windows and precast eyebrow arches that came in three pieces
on a radius. Each window had to be individually measured and
the glass custom cut.
The etched glass with A&M seal and 12th Man statue in
the main entry were shipped from Canada and arrived broken.
The new shipment, weighing 800 lbs., was a challenge to install.
Lifts were taken apart and brought in for the installation
30 ft. above the ground floor.
Bow string trusses spanning 130 ft. over the lobby required
constant supervision. Extensive MEP coordination with subcontractors
was required.
The hydrotherapy pools are suspended over concrete columns
with table tops. The pools' size and potential for damage
prevented drying in the building, so walls had to be left
out until the pools were installed.
Best of 2004-Multifamily Residential
Waterway Lofts
Submitted by: D.E. Harvey
Builders Inc., Houston
Location: The Woodlands
Key Players:
Owner: Threshold Interests
Ltd., Houston
Architect: Ziegler Cooper
Architects, Houston
Structural Engineer: Hanes
Whaley Associates Inc., Houston
Waterway Lofts is a 100,000-sq.-ft. six-story poured-in-place
flat-slab building with a basement, lobby and pool. The exterior,
featuring a Kawneer glass system and brick, envelopes 36 units
of high-end residential lofts overlooking The Woodlands Waterway.
Interior finishes include marble, granite, wood floors and
faux finished walls. The single-level underground garage provides
parking for 72 cars.
Located one block from the Cynthia Woods Mitchell Pavilion
and walking distance from The Woodlands Mall and a variety
of restaurants, the project is the first multistory urban
residential property on The Woodlands Waterway.
Because the project was primarily residential, D.E. Harvey's
role progressed beyond the typical tasks associated with a
general contractor. D.E. Harvey staff became somewhat of an
owner's representative by acting as a liaison between the
tenants and their consultants and the owner. Onsite staff
and subcontractors worked with the tenants' contractors so
that the move-in dates would progress efficiently.
Each unit of the project had to be customized. The customizations
were made during all phases of construction, some coming into
play after the building was substantially completed.
Due to the difficulty in the design of the brick building,
D.E. Harvey went above already high standards of quality control,
despite the cost by adding another consultant on the project
that specialized in waterproofing. The onsite team provided
mock-up models of several residences to ensure quality and
efficiency in the actual construction process.
The project site was constricted and more than 300 yds. from
the street. It was also surrounded by woodlands, and the only
access to the site was via a utility easement. The two streets
flanking the site and a nearby bridge were simultaneously
under construction, and another residential project began
across the street during the project, leaving the team only
one way in and out of the jobsite.
Best of 2004-Airport
Continental Airlines Terminal E
Interiors at George Bush Intercontinental Airport
Submitted by: SpawGlass,
Houston
Location: Houston
Key Players:
Owner: Continental Airlines,
Houston
General Contractor: SpawGlass,
Houston
Architect: Corgan Associates
Architects, Dallas
Structural Engineer: Scientech
LLC, Houston
MEP Engineer: Carter &
Burgess, Houston
Continental Airlines' new 23-gate, 661,000-sq.-ft. terminal
at George Bush Intercontinental Airport helps define the airline's
image. The SpawGlass team was responsible for style, comfort
and efficiency factors during the 30-month, $17.5 million
interiors construction project.
Features of the interiors package included architectural
metal panels, precast stone veneer panels, drywall, paint,
hardware, carpet, stairs, vinyl-composition tile, ceramic
tile and concourse cluster seating. Also, all Federal Aviation
Administration security hardware for gates was included.
The centerpiece of the terminal is the four-story "ellipse,"
which houses the Continental Airlines President's Cub. The
space includes an atrium open from the concourse level to
the roof with a panelized architectural perforated metal screen
in front of storefront windows on each level and an exposed
elliptical steel truss.
Every high wall in the massive space is covered by a custom
fabricated acoustical panel to help absorb and control noise
on the concourse and the third level. A patented outer coating
provides the acoustical properties and also a more durable
finish.
SpawGlass was responsible for the engineering, fabrication
and installation of most of the stairs in the terminal. The
stairs were fitted with ornamental handrails and a modular
railing system with glass panels. The stringers were clad
in brushed stainless steel, which was cut onsite.
Indirect lighting saves energy while providing uniform light.
The flooring is epoxy terrazzo throughout the heavy traffic
areas with carpet in waiting areas.
Terminal E more than doubled Continental's international
gate capacity, making it ultimately capable of processing
4,000 passengers per hour. Almost every piece of equipment
is linked to a building management system, which in turn is
linked to an automated facility maintenance management system.
The terminal is equipped with state-of-the-art plasma monitors
displaying up-to-the-minute flight information. Another automated
system in the terminal known as COBRA matches passengers and
their luggage.
Best of 2004-Education K-12
Richardson High School-Additions
and Renovation
Submitted by: Cadence McShane
Corp., Dallas
Location: Richardson
Key Players:
Owner: Richardson Independent
School District, Richardson
General Contractor: Cadence
McShane Corp., Dallas
Architect: PBK Architects
Inc., Dallas
Structural Engineer: R.L.
Goodson, Dallas
Electrical Engineer: Basharkhah
Engineering Inc., Fort Worth
Richardson ISD significantly improved Richardson High School.
The project was funded via a bond and included an expansion
of 114,000 sq. ft. and renovations totaling 285,000 sq. ft.,
integrating ninth-graders into the existing high school.
This "freshman programming" project includes new
classrooms, science classrooms, a fine-arts department, new
gymnasium, locker rooms and field house. A new culinary arts
department, library, multimedia room, band room, black-box
theater and renovated art rooms, administration parking and
landscaping were also added.
Richardson ISD awarded the $23.2 million project to Cadence
McShane Corp. in September 2002. The company immediately began
making preparations to ensure a timely completion.
A major factor in planning considerations was how to intertwine
on-going construction during classes. The plan was to complete
all the new work except for the fine arts arena by starting
in March 2003 and completing by mid-December. This would allow
the school to make use of the new classrooms and offices while
interior renovation could begin in January.
The new fine-arts addition was completed in early March.
Shortly thereafter the old band hall was converted into a
black-box theater facility. Renovations were completed in
mid-August.
Since some of the renovation work involved upgrades in the
school's power grid and HVAC systems, great care was paid
to student safety. Ultimately the HVAC, power, lighting, ceilings,
fire alarms, flooring and PA systems were replaced with newer
equipment. All restrooms were upgraded to meet ADA requirements.
Although the ISD stipulated a 21-month period for completion
of the project, Cadence McShane was able to finish in just
18 months.
Best of 2004-Private Building
Valero Energy Corporate Campus
Expansion
Submitted by: SpawGlass,
Houston
Location: San Antonio
Key Players:
Owner: Valero Energy Corp.,
San Antonio
General Contractor: SpawGlass,
Houston
Architect: Rehler Vaughn
& Koone Inc., San Antonio
Structural Engineer: Haynes
Whaley Associates Inc., Houston
Civil Engineer: Pape-Dawson
Engineers Inc., San Antonio
Mechanical Engineer: Blum
Consulting Engineers, Dallas
Te Valero Energy Corporate Campus is headquarters to one
of the nation's top oil refining companies. The facility itself,
surrounded by sprawling Live Oak trees, is a limestone and
glass three-level building with a standing seam metal roof
and a glass rotunda in the center flanked with two newly constructed
wings on either side.
When Valero acquired Ultramar Diamond Shamrock in 2001, it
wanted to unite all of its 2,400 employees in one location
and called on SpawGlass to undertake the challenge of enlarging
and renovating the old UDS campus.
The ultimate goal of the project was to create a three-floor,
678,000-sq.-ft. Class A facility with significant renovations
to the overall exterior. Ground was broken in February 2002
on the $92 million renovation, with a 28-month completion
period.
Minimal disruption to Valero employees onsite was achieved
through careful planning by SpawGlass, which split the project
into separate phases. From excavating trees at the site to
performing new construction and improving infrastructure in
the facility's data center, each phase was treated as a different
project although all costs were consolidated into single pay
applications for the owner.
To make room for new construction, 33 trees were carefully
excavated and hoisted by crane to be replanted in a new area
on the campus. Then, two separate SpawGlass crews created
two new wings, while other crews were busy constructing two
new three-level parking garages, adding 1,380 new spaces.
A big job was updating the voice and data center for the
renovated facility. This had to be done early in the building
process as additional equipment had to be installed to accommodate
the needs of the new corporate campus. SpawGlass also obtained
a recertification of the FM 200 fire suppression system vital
for protection of the sensitive gear in the data center.
Best of 2004-Higher Education/Research
Rice University Nanofabrication/Clean
Room Lab Facility
Submitted by: McCarthy Building
Cos. Inc., Addison
Location: Houston
Key Players:
Owner: Rice University,
Houston
General Contractor: McCarthy
Building Cos. Inc., Addison
Architect/Engineer: Lockwood
Greene Engineering & Construction Inc., Dallas
Rice University in Houston selected McCarthy to fulfill the
renovation of its Nanofabrication/Cleanroom Lab Facility in
Abercrombie Hall, which is an expansion of Rice University's
nanotechnology research program. The project offered McCarthy
and its design partner, Lockwood Greene, the opportunity to
develop unique solutions to the goal of taking a 67-year old
existing facility and transforming it into a state-of-the-art
clean-room environment supporting the study and research of
nanotechnology.
The physical size of the facility was small, only 3,000 sq.
ft., but the job had a degree of complexity. To accomplish
the task, it was necessary to demolish interior structures
and completely renovate existing outdated laboratory spaces,
converting them into Class 100 and Class 1000 clean room laboratories,
a conference area and office space. Restroom facilities and
building exterior were upgraded at the same time.
All construction had to be coordinated to minimize disruption
to ongoing laboratory and classroom activities. McCarthy performed
construction after hours, on weekends, nights and holidays.
Following clean-construction protocols, offsite prefabrication
of many components enabled just-in-time delivery of many project
materials. Limited space required strict control of construction
material deliveries.
The construction of the new facility will allow nanotechnology
researchers to study minute mechanisms and configurations
the size of only a few atoms. The emerging area of research
will potentially have profound and positive impacts in the
fields of medicine, technology and agriculture.
Best of 2004-Industrial (Light)
Woodgrain Millwork Manufacturing
Facility
Submitted by: Harrison Walker
& Harper, Paris
Location: Greenville
Key Players:
Owner: Woodgrain Millwork,
Greenville
General Contractor: Harrison
Walker & Harper, Paris
Architect: Alton Parker
& Associates, Dallas
Field Engineer: Stovall
& Associates, Greenville
Woodgrain Millwork is one of the world's largest international
millwork companies. Its origins date back to 1954, with its
first plant in Cedar City, Utah. The company produces high-end
doors, with Home Depot being a primary customer and about
70 percent of business coming from custom orders.
By 2002, Woodgrain was outgrowing the building it occupied.
After several months of searching and negotiating, Woodgrain
accepted an offer from Greenville Industrial Centre, a new
industrial park that was in the process of being developed,
to build a new 123,000-sq.-ft. manufacturing facility.
Work began on Woodgrain's new building simultaneously with
the development of the Greenville Industrial Centre. Intricate
coordination with the owner, city of Greenville, the architect
and the site contractor allowed both projects to be completed
in record time. The $3.7 million Woodgrain Millwork's Atrium
Patio Door project, completed in five months, became the first
tenant of the Greenville Industrial Centre.
The manufacturing facility occupies 10 of the development's
95 acres with an option to add eight more. Support areas include
a high-tech presentation/conference room, a break room, storage
rooms and a large cafeteria that serves double duty as an
employee training room.
The most striking features are two large freestanding tilt-wall
accent panel entrances. Towering 28 ft. tall and 10 ft. from
the exterior walls, they add depth and texture to the exterior
façade. The warehouse/manufacturing is laid out to
maximize efficient workflow for two shifts of employees. Truck
docks are equipped with state-of-the-art dock equipment.
Best of 2004-Masonry
Baylor University Science Building
Submitted by: Brazos Masonry
Inc., Waco
Location: Waco
Key Players:
Owner: Baylor University,
Waco
General Contractor: The
Beck Group, Dallas
Architect/Engineer: HarleyEllis,
Pontiac, Mich.
Masonry is at the heart and soul of the Baylor Science Building
project. All of the exterior walls are concrete masonry unit
backup. The exterior sports an impressive blend of modular
velour and modular scratch-face Baylor Red brick, with cast
stone and custom concrete masonry unit white banding providing
contrast.
The project presented a major scaffolding challenge. For
the block work, frame scaffold was utilized, working from
floor to floor on the inside. The damproofing crew used suspension
scaffolding and a boatswain's chair, while the veneer crew
worked from a heavy-duty crank-up system. Coordination between
the systems and the specific crews was an everyday priority,
with 504,000 sq. ft. of scaffolding at heights of more than
60 ft.
Crews installed 180,000 gray CMU. The details around the
wing section windows made use of three sizes of CMU in a complicated
step-in and step-out pattern. This design was necessary to
accommodate the cast stone/custom concrete masonry unit/brick
exterior. The architect used 31,000 custom CMU , 5,100 sq.
ft. of cast stone and 1,000,000 modular face brick in an accent
banding pattern for the exterior.
At one point, the crew size reached 96 onsite employees.
Making efficient use of staffing, equipment, material and
time, Brazos Masonry was able to complete the $3.7 million
contract in about a 15-month timeframe.
|