Thirst
For Knowledge
New $36.7 Million Experimental Sciences Building Rises On Texas Tech Campus
By Mark Rea
The pursuit of knowledge gained through extensive research
is the reason behind construction of a new Experimental Sciences
Building on the campus of Texas Tech University in Lubbock.
Part of the university's ambitious Campus Master Plan created
in 1996, the $36.7 million facility will feature 127,783 sq.
ft. of space for research laboratories, technology centers
and offices.
"This is just one example of the university's commitment
to providing students with new technology and world-class
facilities," said Dr. David J. Schmidly, president of
Texas Tech. "We have recently completed renovations at
the University Libraries and West Hall, plans to modernize
existing facilities are well under way, and construction on
the English/Philosophy/ Education Complex is finished."
Lubbock-based Lee Lewis Construction Inc. is proving construction
manager-at-risk services for the five-level research facility,
which also features more than 25,000 sq. ft. of basement space
in a building that will include an imaging center, a virtual
reality center and a variety of research laboratories.
"This is a composite steel-and-concrete-masonry-unit
structure," said Chad Henthorn, project manager for Lee
Lewis. "The outer walls are basically CMU, and we have
reinforcing steel bars that are lapped from the basement walls
all the way to where the CMU tops out at the base of the fourth
level. It's basically what holds the structure together."
The basement was constructed on spot footings and its walls
are 17½ ft. tall and 1 ft. thick with a brick ledge
at the top to support the building's brick façade.
Additionally, every cell of each CMU was filled with concrete
for added vibration reduction, vital to the kinds of equipment
to be used in the research laboratories. "It also makes
this an extremely safe and secure structure," Henthorn
said.
More than 65,000 CMUs, 600 tons of reinforcing steel and 1,000
tons of structural and miscellaneous steel comprise the structure.
Construction on the project began in April 2002 with demolition
of an existing parking lot and utility relocation, which included
re-routing a 16-in. water main as well as sewer and natural
gas lines.
Lubbock-based Allen Butler Construction excavated to a depth
of 14 ft. below grade for the basement and removed more than
21,500 cu. yds. of dirt. The excavated material was transported
to a site maintained by Texas Tech to be stored, recycled
and used for future construction projects.
Once excavation was completed, 29 concrete piers containing
approximately 265 cu. yds. each were poured over more than
100 footings. Southern Star of Lubbock supplied the ready
mix concrete, which was poured and formed by Lee Lewis crews.
Structural steel erection began one-third of the way through
basement wall construction.
"That process continued in sequence from framing the
first floor through the third floor," said Lee Lewis
project superintendent Randy Ripple. "As the 19-gauge
composite metal floor decks were installed, concrete slabs
were poured. Then, as the slabs were cured, installation of
the CMUs began."
Vibration Sensitivity
Los Angeles architectural firm Anshen + Allen designed the
Experimental Sciences Building for vibration sensitivity,
and several portions of the concrete floor slabs were poured
to thickness of up to 7.25 in. above the 3-in. metal decks.
On the same floors, where office space will be located, the
slab is only 2.5 in. thick.
"It was kind of unusual to pour such differing thicknesses
of concrete on the same floor," Henthorn said. "It
took a tremendous amount of coordination to get those pours
completed correctly and on schedule."
Ripple designed the formwork for each separate pour and laid
out each wall pour for the dowel work that extends into the
masonry. Reinforcing steel dowels, ranging from No. 4 to No.
8 bars, are embedded into the basement walls with each CMU
containing up to four bars per cell.
"All along the basement wall, there is an average of
at least two bars every 8 in.," Ripple said. "The
sizes were all different, too. For instance, at window jambs,
we used No. 6 bars and then No. 5 bars between the jambs.
Under the windows, we would place No. 4s.
"We couldn't use the same sized bar all the way around.
And different numbers of rebar have different lengths. It
was tricky and took a lot of coordination on that part of
the project."
Five Levels of Research
Five levels of varying size and scope make up the J-shaped
research structure. The basement contains two main laboratories
- a plant growth lab and a Biological Safety Level 3 lab for
sensitive microbiological research projects. Such facilities
are rated on a 1-to-4 scale, with the highest level of 4 given
only to such facilities as the National Center for Disease
Control and Prevention in Atlanta.
Also located on the basement level is shell space for future
expansion, which could include a second Bio Safety Level 3
lab.
The main lobby is located on the 37,708-sq.-ft. ground level.
The lobby is accessed through the western entrance and is
located between two shear walls, which begin with interior
concrete basement walls and continue up through the structure
as a CMU wall with a concrete beam at each level that ties
into the slab.
The first floor will also house a geographical information
systems center, a virtual reality center, research labs, office
space, teaching labs, geonomics and DNA labs and an imaging
center. That center utilizes electron microscopes, which are
extremely sensitive to vibration and led to special design
of the basement walls.
The 27,056-sq.-ft. second level and the 24,480-sq.-ft. third
level contain a pair of large, multisectioned research labs,
and the 13,229-sq.-ft. fourth level contains the building's
mechanical equipment and air handlers.
Unusual Exterior
While the building is being constructed as a functional research
facility, its exterior will feature several unusual architectural
touches to set it apart from most other similar structures.
An outdoor arcade is located on the north side of the building,
which is the top of the J-shape, and along the courtyard,
which is inside the J's hook. A covered walkway will also
be located outside of the building complete with a clay tile
roof and brick pavers to match the Spanish Renaissance style
of architecture located elsewhere on the Texas Tech campus.
Additionally, the arched walkway will feature medallions etched
into the structure by renowned Rockport sculptor Jesus Bautista
Morales and will match another piece of art to be located
between the Experimental Sciences Building and the future
Human Sciences Building.
The Experimental Sciences Building will feature a blend of
more than 350,000 beige and brown bricks installed by Waco-based
Brazos Masonry and a combination of cut white limestone and
cast stone.
A crew of 75 was on the job site in late August, working an
average of six days per week. Henthorn said he expected the
peak of construction to begin at year's end and continue through
next spring when the workforce will jump to 125. Completion
of the project is expected in fall 2004.
| PROJECT
TEAM |
| CONSTRUCTION
MANAGER : |
Lee Lewis Construction
Inc., Lubbock |
| OWNER: |
Texas Tech University
Facilities, Lubbock |
| LOCATION: |
Lubbock |
| ARCHITECT:
|
Anshen + Allen, Los
Angeles |
| STRUCTURAL
ENGINEER : |
John A. Martin &
Associates, Los Angeles |
| MASONRY: |
Brazos Masonry, Waco |
| STEEL
ERECTION: |
Bryan Bennett Enterprises
Inc., Lubbock |
| MECHANICAL,
PLUMBING: |
SkiHi Enterprises Inc.,
Lubbock |
| ELECTRICAL: |
Greer Electric Co. Inc.,
Lubbock |
| CONCRETE
SUPPLIER: |
Southern Star, Lubbock |
| REBAR
SUPPLIER: |
The Lofland Co., Dallas |
| GLASS/GLAZING: |
Jennings Glass Contractors,
Dallas |
| EXCAVATION: |
Allen Butler
Construction, Lubbock |
USEFUL SOURCES
For additional information regarding this project, check
these sources:
An artist's rendering of the completed Experimental Sciences
Building is available on the Internet at http://www.leelewis.com/project%20pages/TTU%20EXPSCI.htm.
To learn more about safety practices used in biomedical
and microbiological laboratories, visit this Web address:
http://www.cdc.gov/OD/ohs/biosfty/bmbl4/bmbl4s2.htm.
|