Running
To Daylight
Expansion of Dallas' Tom Landry Highway May Reach End Zone Two Years Early
By Jack Flanders
Famed Dallas Cowboys coach Tom Landry would be proud of his
new freeway: It's getting bigger and faster and is way ahead
of projections - just what he wanted from his football teams.
Since February, the Texas Department of Transportation and
Fort Worth-based general contractor Gilbert Texas Construction
LP have moved quickly on the first phase of the $97 million,
five-mile widening project.
When completed in 2005, nearly two years ahead of schedule,
the section of Interstate 30 dedicated to the late football
coach will have a new reinforced-concrete surface, one and
sometimes two additional lanes in both directions, and seven
reconstructed bridges.
It is the second largest widening project in North Texas,
topped only by the Loop 635 (LBJ Freeway) and U.S. Highway
75 interchange in North Dallas, better known as High Five.
Statewide it's the third largest project TxDOT has under contract,
according to highway department project engineer Bill Compton.
Built in the late 1950s, the 5-mi. "Tom Landry Highway''
stretch of IH-30 - from near downtown Dallas to Loop 12 to
the west - has had only three lanes in each direction.
For many years, those six lanes have not been enough to handle
burgeoning traffic along IH-30, the oldest interstate link
between Dallas and Fort Worth.
When completed, the newly configured Landry Highway will have
four lanes on each side and, in many places, a fifth lane
for entering and exiting the freeway.
Although originally scheduled for completion in 2007, the
project has moved so quickly it's expected to be finished
in late summer of 2005, said Gilbert Texas project engineer
Knute Henning. A revised construction sequence implemented
by TxDOT and Gilbert Texas is saving a considerable amount
of time, Compton said.
Construction Continues
Last spring, work began on the north side of the project
where a three-lane, 4½-mi. detour is being constructed.
When the detour is completed, traffic will be shifted to the
north and work will begin on the eastbound lanes. The final
phase of the project will include the reconstruction of the
westbound lanes, erection of median barriers, lighting, and
landscaping.
Throughout the summer, Gilbert Texas' crews worked to erect
retaining walls between Sylvan Avenue and Hampton Road.
"About every 5 ft., we placed a drilled shaft 30 to 36
in. in diameter. A steel reinforcing cage and concrete are
placed in each shaft,'' Compton said. "Once the shafts
have cured, the earth along one side of the shafts is removed
down to a new finished grade, and a precast panel wall fascia
is installed by the contractor. There are about 103,000 sq.
ft. of wall like this, totaling about $9 million."
An additional 230,000 sq. ft. of retaining walls are being
built using various wall systems, including soil nailing,
rock nailing and mechanically stabilized earth. These walls
will add another $7 million to the project, Compton said.
"We incorporated a large amount of retaining wall so
we could limit the need for additional right of way, which
is generally expensive and difficult to obtain in urban areas,"
he added.
By mid-August, Gilbert Texas crews had excavated 346,000 cu.
yds. of material, and is expected to remove 1.3 million yds.
by the time the project is complete. To remove the material,
workers are using scrapers and excavators, including 400-series
and Cat 365 equipment. The material is being removed in 35-ton
Volvo off-highway trucks, tandems and semi-trucks.
On the south side of the eastern end of the project, the area
nearest to neighborhoods, 4,700 ft. of noise wall will be
added to retaining walls. The cast-in-place noise walls, measuring
either 8 or 12 ft. in height, will be visible from the freeway,
but not the retaining walls.
"For the noise walls, we're using an architectural form
liner that allows us to add murals," Henning said. "The
murals will be in-relief, and nearby architectural columns
will include steel emblems of Tom Landry's famous hat.''
Addition By Subtraction
While constructing retaining walls, crews also replaced the
Edgefield and Fort Worth avenues overhead bridges. The Edgefield
Avenue bridge was closed, but will be reopened later in the
project. The Fort Worth Avenue bridge is being reconstructed
and expanded in stages to include sidewalks and architectural
railing.
To keep from closing the bridge entirely, Gilbert Texas crews
demolished half the bridge and moved all traffic onto the
remaining older section. When the new section was completed,
the process was repeated on the older half.
The ramp to the southbound Hampton Road overhead also has
been removed and will be rebuilt later to accommodate the
wider freeway.
Structural steel beams and reinforced concrete decking are
being used on all three bridges. Each has a conventional concrete
substructure supported by a drilled-shaft foundation.
Along with its extra lanes, the freeway will have an upgraded
surface. Previously a concrete roadway with asphalt overlay,
the new surface will be strictly reinforced concrete.
Due to soil types along the existing roadway, it was determined
that the use of lime-treated subgrade not be used. In its
place, the western portion of the project, which contains
poor in-situ soils, is being excavated 2 additional ft. and
the soil replaced with better material. To compensate for
the additional strength usually provided by the addition of
lime, a thicker than usual asphalt-concrete pavement base
is being used.
The final pavement section will have 7 in. of asphalt-concrete
pavement and 13 in. of continuously reinforced concrete pavement.
The project will require about 490,000 sq. yds. of reinforced
concrete pavement and 230,000 tons of asphalt, according to
TxDOT.
Because so much concrete will be needed, Gilbert Texas erected
its own batch plant near the site. The plant is able to produce
about 250 cu. yds. of concrete per hour, which allows placement
of up to 2,500 yds. per day.
"We'll pour sections 12 to 24 ft. wide, and there will
be hundreds of pours,'' Henning said. "How much we will
pour each day depends on how much material the batch plant
can turn out.''
Various equipment will be used to lay the concrete, but the
two main units will be a Gomaco 2600 placer and a Gomaco 4000
paver. They have expandable frames that allow for different
widths.
Scheduled to begin next year, concrete pours on the permanent
roadway will start on the west end and move eastward. Traffic
will be moved north and south as new lanes are constructed.
Despite its high profile, the widening of Tom Landry Highway
is only one phase of a broader IH-30 widening program that
has been under way for 10 years. When completed, the interstate
highway will be expanded from downtown Dallas to the Tarrant
County line - a distance of about 20 miles.
| PROJECT
TEAM |
| GENERAL
CONTRACTOR : |
Gilbert Texas Construction
LP, Fort Worth |
| OWNER: |
Texas Department of
Transportation, Austin |
| LOCATION: |
Dallas |
| ARCHITECTS:
|
Turner Collie &
Braden Inc., Dallas; Carter & Burgess Inc., Fort Worth;
LopezGarcia Group, Fort Worth |
| DRILLING: |
ATS Drilling LP, Round
Rock |
| UTILITY
PLACEMENT, RELOCATION: |
Renaissance Construction
Inc., Justin |
| ASPHALT
PAVING: |
APAC-Texas Inc., Dallas |
| REBAR
PLACEMENT: |
D'Ambra Steel Services
Inc., Houston |
| TIEBACKS/SHORING: |
Craig Olden Inc., Little
Elm |
USEFUL SOURCES
For additional information regarding this project, check
these sources:
The widening of Interstate 30 in Dallas is part of TxDOT's
ambitious Pegasus Project, which has its own Web site at www.projectpegasus.org/overview.htm.
Maps of the Tom Landry Highway and other major Metroplex
roadways are available at www.metroplexdaily.com/tips-traffic.asp.
|