TxDOT Completes
First Asphalt Perpetual Pavement Project
Stretch of IH 35 Near Waco Features
Several Different Mixes
By Mark Rea
The Texas Department of Transportation - always exploring
more cost-efficient ways to get motorists to and from their
destinations - has completed its first project using perpetual
asphalt pavement.
On a 2.56-mile stretch of Interstate 35 just north of Waco,
TxDOT in mid-June completed a roadway that has a 20½-in.
hot mix asphalt concrete pavement, believed to be among the
thickest ever recorded on a hot mix project in Texas.
Costing nearly $21 million, the project will serve as a pilot
program for TxDOT as it searches for alternatives to the concrete
pavement used throughout much of the state's high volume roadway
system
"A big part of why we did this project was the interest
of the Texas Asphalt Paving Association," said Duane
Schwarz, TxDOT's Waco district director of construction. "Along
with other parties in the hot mix industry, the state association
wanted to develop a bituminous design that would compete against
concrete on roadways like Interstate 35.
"The association knows about all of the future work we
have scheduled for IH 35 and other major roadways throughout
the state, so it got together with highly qualified industry
experts, and designed the pavement structure for this particular
project."
To develop the unique blend of design mixtures for this project,
TxDOT worked with a group that included Dr. Jon Epps, professor
emeritus of the University of Nevada at Reno and past president
of the executive committee of the International Society for
Asphalt Pavements, the Asphalt Paving Institute and Charles
Smoot, director of technology for TxAPA.
After removing the center grass median for additional northbound
and southbound lanes, crews placed 10 in. of lime-treated
subgrade atop an additional 6 in. of base material for the
new pavement. The result will provide IH 35 with three lanes
of traffic in both directions divided by a concrete median.
The pavement itself consists of six courses of hot mix material,
each featuring its own unique mixture.
Atop the subgrade and base material is 4 in. of Superpave
hot mix asphalt concrete pavement designed to contain high
asphalt content and low air void. The mix carries a 98 percent
laboratory density and a performance graded binder rate of
70 degrees to minus-22 degrees Celsius. (That computes to
a temperature range the mixture can withstand of 158 to minus-7.6
degrees Fahrenheit.) It is virtually impermeable to ground
water and is designed to resist any fatigue cracking as well
as withstand nearly every adverse weather condition.
"This particular mixture has additional asphalt to make
it more flexible and resistant to fatigue," Schwarz said.
"The higher density is something TxDOT doesn't normally
specify. Normal specs call for 96 percent lab density and
this has a 98."
Two separate layers of 1-in.-sized stone-filled hot mix asphalt
concrete pavement goes atop the Superpave. These layers -
5 in. each - have the same PG binder grade used in the first
layer and are 4.6 percent liquid asphalt.
Next comes 3 in. of three-quarter-inch-sized stone-filled
hot mix asphalt concrete pavement with 4.8 percent liquid
asphalt followed by 2 in. of half-inch heavy-duty stone matrix
asphalt, or SMA, concrete pavement with a higher asphalt rating
of 6 percent. The latter mixture includes cellulose fibers
and a mineral filler of very fine dust to help fill voids
between rocks to keep moisture out. The mixture features only
4 to 5 percent air voids.
Finally, 1½ in. of permeable friction course, widely
known as PFC, made with cellulose fibers, completes the perpetual
pavement. All of the rocks in the final mixture are one size,
which helps the layer to have stone-on-stone contact, but
about 20 percent air voids. This layer is so porous that surface
water can trickle through. But once moisture reaches the layer
of SMA, it does not seep through and flows to the edges and
out of the pavement, leaving a water-free surface on top to
reduce hydroplaning.
Break In Schedule
Work crews from Waco-based Young Contractors Inc. began completing
the final phase of the project in early May by placing the
top PFC layer.
The project began in January 2001 and was originally designed
to be completed in late 2002.
"We completed the SMA portion of the project last year
right around Thanksgiving," said Young Contractors project
superintendent Homer Pricer. "But our engineer recommended
not trying to lay the final PFC in the wintertime because
that mix is so porous."
"And TxDOT agreed with that assessment. We didn't want
to risk that the mixture could flash-cool and create too many
problems laying and compacting the mix. So with the cold weather
and holidays coming, we decided to shut down the job until
we got to warmer weather."
Schwarz added that the specifications "require warm temperatures
- 60 degrees surface temperature - and the material can cool
fairly quickly. Since we were doing the work at night, it
was going to be hit or miss in terms of whether or not the
temperature would be warm enough. We felt that we would alleviate
a lot of headaches if we just shut the paving down and returned
in warmer weather. It was a TxDOT decision that came down
to wanting the project completed correctly rather than just
getting it finished."
To further ensure perfect cooling conditions for the mixture
once the project resumed, Young Contractors finished paving
at night after completing most of the other portions of the
roadway during daylight hours. Workers typically began to
close lanes on IH 35 about 9 p.m. while the first hot mix-laden
trucks began to appear at the project about 11 p.m.
"We usually got off the road by 6 a.m. before the morning
commute began," Pricer said. Work on the northbound lanes
of IH 35 was completed first and opened to traffic before
crews turned their attention to the southbound lanes.
While installing the final PFC layer, crews used approximately
700 to 800 tons of hot mix asphalt from Young Contractors'
own hot mix plant, located about eight miles from the project
site. The entire project contains more than 167,000 tons of
HMA.
The new, seamless 12-ft.-wide main lanes were placed over
the same base course used when this section of IH 35 was built
in 1967. The existing 10 in. asphalt courses were removed
and some was recycled as part of the roadway shoulder while
the rest was stockpiled for later use in other projects.
New Mixes, Challenges
Working with advanced mixes led to some unique challenges
for work crews, especially in the area of machinery maintenance.
"Just learning how to put down the different kinds of
mixes and prevent clogging in our machines was the one of
the major differences as opposed to working with what we consider
normal hot mix," Pricer said. "Some of this new
asphalt is extra sticky, and it doesn't fall off the belt
of the transfer machine like other mixes, so clean-up was
sort of a trial-and-error process.
"For example, when we began one of the courses, we had
to pull the transfer machine offline three to four times a
day just to clean it. As the project continued, though, we
didn't experience the same problems. We learned a lot as we
went along. As far as the actual laying of the mixes was concerned,
asphalt is asphalt. It all goes down on the course pretty
much the same."
On the final PFC course, Young Contractors used several different
pieces of equipment, including transfer and laydown machines
and two steel rollers. A water truck was also employed as
well as a pickup truck to pull the power plant for the portable
lights. Tying in bridgework involved loaders, motor graders
and brooms. Each piece of equipment had its own individual
operator with an additional 14 workers on the laydown crew
to help fill in the course and perform clean-up tasks.
When the SMA course was installed, Young Contractors utilized
additional rollers.
"In addition to the breakdown roller with a steel wheel,
we used a pneumatic roller and then a finish roller,"
Pricer said. "The pneumatic roller smoothes the course
a little better and brings up some of the fine material to
the surface to cover the other larger aggregate."
More Perpetual Projects?
Schwarz said that from his perspective, "The jury is
still out on the perpetual pavement concept. I don't know
whether TxDOT will continue to do a lot of this or not. I
would suppose a lot will depend upon how this particular project
is received."
Nevertheless, there is already another perpetual pavement
project on the design table. TxDOT is scheduled to let a perpetual
pavement project in August for a stretch of IH 35 near the
point in Hill County north of Hillsboro where the roadway
splits to go northwest toward Fort Worth and northeast toward
Dallas
"It will be almost identical to this design," Schwarz
said. "We have picked up a lot of excellent information
from this project for other locations, such as using the SMAs
and PFCs in other combinations. And while those projects would
not be considered perpetual pavement roadways, there has been
a lot of valuable data and experience gained from working
with these particular mixes."
PROJECT TEAM
GENERAL CONTRACTOR/HOT MIX SUPPLIER:
Young Contractors Inc., Waco
OWNER: Texas Department of Transportation
LOCATION: Interstate 35, Waco
AGGREGATE SUPPLIER: Hanson Aggregates,
Davis, Okla.
|